Skip to main content
European Commission logo print header

Offshore Wind Turbine Towers – A Quicker, Cheaper Flange Supply Route

Cel

There is a tendency to higher power offshore wind turbines, leading to larger turbine towers (5m diameter and greater) and a requirement for large diameter connection flanges between the tower sections and between the tower and foundation transition pieces. Currently, forged rings are specified, with inherently high cost and few suppliers worldwide. This leads to long lead times and higher costs for these strategic parts.

RingMan will develop an alternative manufacturing route (using lower-cost cold rolled plate) which will enable the fabrication of large diameter wind tower flanges to be undertaken by our SME consortium members.

The project will enable the partners to commission:

• Development of high quality, low distortion, thick section electron beam welding fabrication and machining to produce flanges from readily available cold rolled steel plate material.
• Understanding of the flange property requirements and how these can be met by a fabricated flange leading to design tools to enable wind turbine tower designers to specify these products.
• Procedures for inspection that will aim to ensure that the parts manufactured meet or exceed the required performance properties.

Zaproszenie do składania wniosków

FP7-SME-2011
Zobacz inne projekty w ramach tego zaproszenia

System finansowania

BSG-SME - Research for SMEs

Koordynator

SANBORN AS
Wkład UE
€ 337 417,00
Adres
ZBRASLAVSKA 27 MALA CHUCHLE
15900 PRAHA
Czechy

Zobacz na mapie

Rodzaj działalności
Private for-profit entities (excluding Higher or Secondary Education Establishments)
Kontakt administracyjny
Zak Anthony (Mr.)
Linki
Koszt całkowity
Brak danych

Uczestnicy (6)