PV RURAL ELECTRIFICATION OF 79 ANDALUSIAN DWELLINGS

Ziel

To demonstrate that isolated rural areas in regions of high annual irradiance, unconnected to the grid can be electrified by photovoltaic systems. Detailed load analysis in the different sites have been made and the sociological effects in the small rural communities have been studied. (Acceptance of electrification).
The systems operate since October 1988 (on DC) and since October 89 (on AC), but there were previous and subsequent problems with the inverters, especially at the Rio Madera (!). Two sites (I and III) are now to be connected to the grid and the pv systems shall be possibly used for grid boosting.
The knowledge obtained through this project by the contractor (Compania Sevillana de Electricida) to solve technical and social problems is a valuable experience for future pv projects.
79 dwellings are electrified with 39 individual and centralised sub-systems. At the five locations different subsystems are installed.
220 AC: at sites I, II, IV, V: centralized; at site III: individual.
24 V DC: at site IV, V: centralized; at site III: individual.
12 V DC: at site II: centralized.
I: RIO MADERA. 27 houses. At that site, with grouped houses, a new grid has been installed. Local grid: air lines, typically several hundert meters long.
II: LOS MORALEJOS. 17 houses. The houses have already individual.
12 V DC supplies, which have been modernized. An additional grid has been installed.
III: PRADOS DELLA PRESA. 15 houses. At this site with isolated houses, 12 houses have been equipped with an autonomous 24 V DC supply and a 220 V AC supply, three houses with 12 V DC supply. No local grid is installed. IV: FUENTE DE LA HIGUERA. 14 houses. The existing, autonomous 12 V installation has been replaced by a 24 V DC grid and a supplementary grid has been installed.
V: LA CANALICA. 6 houses with systems similat to site IV.
Nr. of subsystems : I:3. II:1(central)+17 indiv. III:15 indiv. IV: 3. V:1
Power of subsystems : I: 2.7+3.6+3.6 = 9.9 kW. II: 2.4 kW +0.8 kW
= 3.2 kWp. III:4.6 kW.
IV:3 x 0.9 kW=2.7 kWp. V: 1.1 kW
Total power : 21.5 kWp
Backup : Diesel (4 kW) at sites I and IV
Number of modules : 396
Module description : 214 ISOFOTON type M-40-L.
62 ISOFOTON type M-75 -L.
120 ISOFOTON type ISO-90.
Some of the modules, used at site I and III, are double-sided.
Connection : connected to 12, 24 od 120 V DC Support : on metallic structures for the centralized systems, sites I and II. On 7 m high steel tower at site IV. On "solar trees" at site III and site V.
Max power tracker : none
Charge controler : ATERSA type 12 CRC-15 TD
Battery : FEMSA 1xType: 9AEF1125-1; 2x16AEF2480-1; 12x3AEF180 -1;12x2AEF120-1;
3x5AEF300-1;1x8AEF1000-1; 1x5AEF621-1
Capacity for Site : I II III IV V
Batt. (V) 120 V 24 V+12 V 24 V 24 V 24 V
Batt. (Ah) 1125 Ah 2480+5170 Ah 2417 Ah 2480 Ah 1300 Ah
Batt. (kWh) 168 kWh 59 + 62 kWh 58 kWh 59 kWh 31 kWh
Inverter : All inverters are supplied by PASSCO
Inv. in(V) 120 V 24 V 24 V 24 V 24 V
Inv. out(V) All: 220 V, 50 Hz
Inv. power(kW) 4.6 1.6 11 x 0.5 1.6 0.5 Load description : lighting of houses and public places by 20 or 35 W low pressure. Sodium vapour lamps. Also TV from DC supplies. Refrigerators and other household appliances from AC inverters. Monitoring : Analytical monitoring at site I, Global monitoring at all other sites.

Aufforderung zur Vorschlagseinreichung

Data not available

Koordinator

COMPANIA SEVILLANA DE ELECTRICIDAD
EU-Beitrag
Keine Daten
Adresse
AVDA. DE LA BORBOLLA 5
41004 SEVILLA
Spanien

Auf der Karte ansehen

Gesamtkosten
Keine Daten