THE INSTALLATION OF A SMALL HYDROELECTRIC GENERATING UNIT IN A WATER SUPPLY CANAL

Obiettivo

The installation of a tubular turbine/generating unit in a water supply aqueduct. The anticipated annual energy output is 4,170,000 KWh and the unit cost of energy production is 3. 32 Drs/KWh.

The installation of a small hydroelectric generating unit in the Mornos - Athens aqueduct is expected to take advantage of the relatively constant water flow therein. The design parameters of the unit are as follows;
Turbine Head 8. 0 m
Flow 7. 3 m3/s
Output 600 kW
Speed 400 rev/min
Type Tubular
Generator Rating 700 kVA
Voltage 400 V, 50 Hz, 3 phase.
Type Asynchronous
The electricity produced will be connected to the grid at 20 kV.

Argomento(i)

Data not available

Invito a presentare proposte

Data not available

Meccanismo di finanziamento

DEM - Demonstration contracts

Coordinatore

PUBLIC POWER CORPORATION (PPC)
Contributo UE
Nessun dato
Indirizzo
HEP DEV. DEPT 56-58 AGISIALOU STR.
10436 Athens
Grecia

Mostra sulla mappa

Costo totale
Nessun dato