STANDARDIZATION OF PELTON SINGLE NOZZLE MICROTURBINES WITH OR WITHOUT ADJUSTMENT OF THE FLOW RATE TO MULTIPLIER

Cel

To construct, install and test a range of standardised PELTON microturbines of simplified construction. The design has been standardised in order to obtain an economic scale of design, construction and installation whilts maintaining high efficiency.
The plant have been realized generally respecting the technical characteristics foreseen during the project.
Having the conditions of nominal head stage, the development power is the same above mentioned and we expect an energy output yearly included between 40-60% of the theoretic maximum value for the plant TP 400.
The project was based on two different layouts of microturbine : one grid operations and one isolated operations.
One of this has been concluded (type TP 400 isolated operation); the second, due to the unavailability of adequate site, until is not concluded.
The details of the site isolated operation are :
PLANT 1 PLANT 2
(TP 400)
Site name Piuro (SO)
Head (Mt) 170
Flow (Mc/s) 0.015
Generator output (kW) 15
Diameter of turbine (mm.) 400
Turbine speed (rev/min) 1500
Generator speed (rev/min) 1500
Generator type Synchronous
Rapporto di trasmissione R = 1:1
Mode of operations Isolated
The turbine design has been standardised to produce a range of 8 different runner diameters. By modifying the electrical control pannel the hydraulic machines can operate grid or isolate mode. The electricity generated by the plant is used in the following ways : private utilization in mountain small holiday homes. The plant is utilised six month/year from March to September.

Temat(-y)

Data not available

Zaproszenie do składania wniosków

Data not available