Cel To develop a combined cycle linking the world biggest circulating fluidised bed boiler (600 Mwth) fed with run-of-mine coal and a gas turbine the exhaust of which will be used for feed water heating.The innovative parts concern :The extrapolation of data already acquired on CFB generators of lower capacity will lead to the conception of the present generator using shapes proportional to and with numbers of specific elements directly resulting from those necessary in CFB boilers of 125 MWe. The single boiler furnace will be of a record size for a CFB. 4 cyclones and 4 outside beds will complete this unit. The project will constitute the necessary technological stage towards the design of even larger CFB generators.Also, in the present case, exhaust gas from a gas turbine will replace the bleed steam which is normally used for feed water heating. This layout will increase the efficiency of producing electrical power.This project consists of the construction and setting into operation of a circulating fluidised bed boiler in the Provence power plant of Gardanne in France, together with a gas turbine, the exhaust gas sensible heat from which will be used for reheating boiler feed water, is replacing the bleed steam from the turbo-generator of 250 MWe which is linked to it.Main characteristics of boilerOperating conditionsSteam output 700 t/hSuperheated steam pressure 163 barsSuperheated steam temperature 565 deg. CSteam pressure to reheat 39,5 barsReheated steam pressure 36,5 barsReheated steam temperature 565 deg. CFuel input 149 t/h averageUp to this present day a generator of such a size, fired using a circulating fluidised bed does not exist. Extrapolation to this capacity taking into account the proposers acquired experience leads the following :- a single furnace of a sizenot yet existing but including in its lower part two fluidization grates of a geometry comparable with the biggest existing boilers.- four separation cyclones of such a diameter that one can determine with safety the performances.- four external fluid bed heat exchangers, two of which are assigned to superheating and reheating with adjustment of steam temperature by adjusting the flow of solids through them, and two others assigned to maintain the ideal temperature of the furnace whatever the boiler load.In addition the project foresees feed water heating in the boiler by means of a waste heat recovery boiler on the gases issued from a gas turbine, integrated into the supply system. These gases take the place of the average and low pressure bleed steam from "groupe 4" turbo-generator.The thermal characteristics of the gas turbine and waste heat boiler are the following :a) gas turbine- gross output : 38,4 MWe- auxiliary consumption : 0,12 MWe- natural gas flow : 140 Mwthb) recovery boiler- an economizer (low pressure) 28,1 Mwth- an economizer (high pressure) 36,1 Mwth Program(-y) ENG-THERMIE 1 - Programme (EEC) for the promotion of energy technology in Europe (THERMIE), 1990-1994 Temat(-y) 7.4 - PRESSURIZED FLUIDIZED BED COMBUSTION Zaproszenie do składania wniosków Data not available System finansowania DEM - Demonstration contracts Koordynator EDF/CDF Wkład UE Brak danych Adres 2 RUE LOUIS MURAT 75008 PARIS Francja Zobacz na mapie Koszt całkowity Brak danych