Objective
The strategic goal of the ELYntegration Project is the design and engineering of a robust, flexible, efficient and cost-competitive single stack Multimegawatt High Pressure Alkaline Water Electrolysis of 4,5 T H2/day capable to provide cutting-edge operational capabilities under highly dynamic power supplies expected in the frame of generation/ transmission/ distribution scenarios integrating high renewable energies (RE) shares.
The final design of the MW HP AWE will be achieved on the basis of the development, validation and demonstration of a HP AWE industrial prototype of 250 kW (250 HP AWE) (TRL 7) comprising:
- cylindrical stack consisting of industrial size elementary cells (1,600 mm cell diameter)
- balance of plant (BOP)
- power electronics
- advanced communication & control system
In the early phase of the development process, great attention will be brought to the identification of end-user’s needs and relevant/critical operational requirements.
The target behaviour of the industrial prototype will be thoroughly demonstrated in an operational environment reflecting different on-grid integration schemes using power facilities already available to the Consortium (notably, 635 kW wind and 100 kW photovoltaic power plants).
As previously mentioned, the successful demonstration of the industrial prototype will be paving the way towards the implementation and the commercial deployment of the 4.5 T H2/day HP AWE technology in the frame of large scale demonstration projects which shall be the next step after the conclusion of ELYntegration.
Fields of science (EuroSciVoc)
CORDIS classifies projects with EuroSciVoc, a multilingual taxonomy of fields of science, through a semi-automatic process based on NLP techniques. See: https://op.europa.eu/en/web/eu-vocabularies/euroscivoc.
CORDIS classifies projects with EuroSciVoc, a multilingual taxonomy of fields of science, through a semi-automatic process based on NLP techniques. See: https://op.europa.eu/en/web/eu-vocabularies/euroscivoc.
- engineering and technology electrical engineering, electronic engineering, information engineering electronic engineering control systems
- engineering and technology environmental engineering energy and fuels renewable energy
- natural sciences chemical sciences electrochemistry electrolysis
- social sciences economics and business business and management business models
- engineering and technology electrical engineering, electronic engineering, information engineering electrical engineering power engineering electric power transmission
You need to log in or register to use this function
We are sorry... an unexpected error occurred during execution.
You need to be authenticated. Your session might have expired.
Thank you for your feedback. You will soon receive an email to confirm the submission. If you have selected to be notified about the reporting status, you will also be contacted when the reporting status will change.
Programme(s)
Multi-annual funding programmes that define the EU’s priorities for research and innovation.
Multi-annual funding programmes that define the EU’s priorities for research and innovation.
-
H2020-EU.3.3. - SOCIETAL CHALLENGES - Secure, clean and efficient energy
MAIN PROGRAMME
See all projects funded under this programme -
H2020-EU.3.3.8.3. - Demonstrate on a large scale the feasibility of using hydrogen to support integration of renewable energy sources into the energy systems, including through its use as a competitive energy storage medium for electricity produced from renewable energy sources
See all projects funded under this programme
Topic(s)
Calls for proposals are divided into topics. A topic defines a specific subject or area for which applicants can submit proposals. The description of a topic comprises its specific scope and the expected impact of the funded project.
Calls for proposals are divided into topics. A topic defines a specific subject or area for which applicants can submit proposals. The description of a topic comprises its specific scope and the expected impact of the funded project.
Funding Scheme
Funding scheme (or “Type of Action”) inside a programme with common features. It specifies: the scope of what is funded; the reimbursement rate; specific evaluation criteria to qualify for funding; and the use of simplified forms of costs like lump sums.
Funding scheme (or “Type of Action”) inside a programme with common features. It specifies: the scope of what is funded; the reimbursement rate; specific evaluation criteria to qualify for funding; and the use of simplified forms of costs like lump sums.
FCH2-RIA - Research and Innovation action
See all projects funded under this funding scheme
Call for proposal
Procedure for inviting applicants to submit project proposals, with the aim of receiving EU funding.
Procedure for inviting applicants to submit project proposals, with the aim of receiving EU funding.
(opens in new window) H2020-JTI-FCH-2014-1
See all projects funded under this callCoordinator
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
22197 Huesca
Spain
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.