Demonstration of a 1-MW wave energy converter integrated in an offshore wind turbine farm

Objective

The aim is to develop and install a pre-commercial wave energy converter (WEC) of 1MW power, the WAVESTAR C6-1000 device, with main targets the device industrialization and the demonstration of wind and wave energy applications. The utility company Parkwind, which develops, builds and operates wind farms in the North Sea, is committed to the achievement of WAVESTAR’s next development stage. Parkwind provides the installation site with grid connection for the first full-scale WAVESTAR WEC, located within a Belgian offshore wind farm. The UPWAVE project consortium has been developed through the establishment of strong synergies and partnerships, by bringing together key European industrial players and European universities represented by wave energy experts whose overall objectives focus on:

1) Reduction of the device’s cost by introducing new design, components and materials. Cost optimization is achieved through new methods on deployment, installation, operation and maintenance.

2) Improvement of the energy efficiency by developing a more advanced Power Take Off based on a second generation digital hydraulic system and innovative control strategy.

3) Integration of wave energy converters in wind farms by considering the interaction between wave and wind devices in terms of operation, cost reduction and maximization of environmental benefits.

Public research programs, industrial cooperation and technology transfer from the offshore industry (offshore wind, oil and gas) ensure the development of manufacturing processes, automation and optimisation of the WAVESTAR C6-1000 WEC. New certificates and standards will be made available for the wave energy industry. After the completion of the UPWAVE project, the cost of wave energy will be significantly reduced to a level in line with the cost of offshore wind energy (around 15 c€/kWh). The WAVESTAR C6-1000 demonstrator device will lead to a commercial WEC and a hybrid renewable energy device (wind and wave).

Keywords

Programme(s)

Topic(s)

Funding Scheme

IA - Innovation action

See all projects funded under this funding scheme

Call for proposal

(opens in new window) H2020-LCE-2014-2015

See all projects funded under this call

Coordinator

WAVE STAR AS
Net EU contribution
€ 11 775 225,00
Address
ALSION 2
6400 Sonderborg
Denmark
SME
Yes
Region
Danmark Syddanmark Sydjylland
Activity type
Private for-profit entities (excluding Higher or Secondary Education Establishments)
Links
Total cost
€ 16 821 750,00

Participants (8)