Phase 3 of this collaborative project between British Steel, Hoogovens and Italsider consists of the demonstration of three full coal/oxigen injection trials each of ten weeks duration. The target coal injection rate for the first trial will be up to 100kg/ton hot metal; the target for the third trial will be up to 300 to 400 kg/ton hot metal. The trials will be carried out using equipment already installed and commissioned on a 1000 tons per day blast furnace producing foundry iron at Cleveland Works during phases I and II of the project. Each ten week injection trial will be followed by an analysis and appraisal period. This is the final phase of the project aimed at further reducing coke rates.