Objectif Two 150 kW HMZ horizontal axis wind turbines will be installed and operate at Villacidro-Sardinia in order to provide the necessary electrical energy to the water treatment system of the industrial area. It will be possible to evaluate the contribution of wind energy and estimate the efficiency of such a system for industrial applications. The estimated annual yield is 525 000 kWh.The wind turbines have been installed in May 1986. Connection with the grid took place in September 1986. The annual energy production was 200000 kWh.Two horizontal axis HMZ 150 KW commercial wind turbines were connected to the local grid of the industrial area of Villacidro-Sardinia. The electricity was used by the 500 KW water treatment system and the excess energy requirements was provided by the grid. This project has been carried out in order to evaluate the contribution of wind energy and to estimate the efficiency of such a system for industrial applications.The total project will cost 1.169.600.000 LIT; only the part which corresponds to one machine i.e 828.100.000 LIT will be supported. The total annual yield is estimated to 525.000 KWh, with a calculated payback of 12 years. The local cost of energy (island grid) is 165 LIT/KWh while the cost of electricity produced by the wind generator is 110 LIT/KWh. Programme(s) ENG-ENALT 2C - Programme (EEC) of demonstration projects relating to the exploitation of alternative energy sources and to energy saving and the substitution of hydrocarbons, 1983-1985 Thème(s) Data not available Appel à propositions Data not available Régime de financement DEM - Demonstration contracts Coordinateur Consorzio per la Zona di Sviluppo Contribution de l’UE Aucune donnée Adresse Via Rovereto 6 09100 Villacidro Cagliari Italie Voir sur la carte Coût total Aucune donnée