THE HYDROELECTRIC DEVELOPMENT OF THE OLD WATER MILLS OF PRADES

Ziel

To use a simplified modular design of Kaplan turbine, which is also easy to construct and install, at an old mill site whilst ensuring that the historic nature of the site is preserved. The expected energy output from this project is 1,602,700 kWh annually.
The contractor has experienced problems with difficult ground conditions, two floods, which destroyed the dam, and silting up of the tail race. First trials with the power house equipment took place after connection to the public supply authority, EdF.
Precautionary measures are being installed to avoid future flood damage but negotiations have not yet been completed with the main fishing society on the provision of suitable fish passes.
An axial flow Kaplan turbine, with modular components for ease of maintenance, is installed in an old mill site. Care has been taken with the design of the installation to retain the historic features of the original installation by using existing buildings to house much of the electrical equipment, by integrating the tail race into its surroundings, and by ensuring that upstream plant has minimal environmental impact. Two fish passes are also incorporated in the design.
Turbine details :
head - 2.9 m
flow - 17 m3/s
power - 411 kW
speed - 136 rev/min
Asynchronous generator details :
power - 325 kW
voltage - 660 V
speed - 1000 rev/min
The unit cost is 0.272 FF/kWh.

Thema/Themen

Data not available

Aufforderung zur Vorschlagseinreichung

Data not available

Koordinator

COMMUNE DE STE. ENIMIE
EU-Beitrag
Keine Daten
Adresse
LANGUEDOC ROUSSILLON
48210 SAINTE ENIMIE
Frankreich

Auf der Karte ansehen

Gesamtkosten
Keine Daten