PV POWER FOR MUNICIPAL INSTALLATIONS: TOILETS, BUS-STOPS

Objective

To demonstrate the feasability of pv power for isolated bus stops and public toilets in order to avoid installation of electric power lines.
The installations are operating.
Three types of equipment are used:
1.) Shelters at bus stops (288 W), 22x288,
2.) Poles at bus stops (4 W), 10*4,
3.) Public toilets (96 W), 3x96.
The equipment is prefabbricated and can be transported to the installation site by lorry with crane.
Nr.subsystems : 33
Power subsys. : 4 + 96 + 288 Wp
Total power : 5.5 kWp
Backup : none
Nr. of modules : 136 (20*6 + 3*2 + 10)
Module descrip. : Shelters: Photowatt BPX, 48 Wp.
Poles: Equinoxe EQS 4/12, 4 Wp.
Toilets: Equinoxe EQD 24/12, 24 Wp.
Connection : various
Support : On the roofs of the bus shelters, with 15 deg. inclination (quasi invisible, to avoid vandalism).
Max.pwr.trcker : non
Chrg.controler : data not available
Battery : Bus shelter Bus stop Toilet
STECO, Saphir 1600 Ni-Cad STECO, Saphir 1100
Capacity : 24 V6
Batt. (Ah) : 185 5 2 x 124
Batt. (kWh) :
Inverter : none
Load descrpt. : Bus shelter: Fluorescent lamps (18 W) with automatic switching, 2 hours after twilight and 2 hours before dawn.
Bus stop: Illuminated timetable for the buses with automatic light emitting diode indicator for the next bus.
Toilet: Fluorescent lamp (7W) during utilisation of the toilet, with passive infrared detector.
Monitoring : Irradiance, produced energy and used energy are recorded.

Call for proposal

Data not available

Coordinator

SYNDICAT INTERCOM. TRANSPORTS URBAINS DE CHALONS
EU contribution
No data
Address

71321 CHALONS-SUR-SAONE
France

See on map

Total cost
No data