WINDFARMS DIFFUSION START IN PUGLIA ROSETO VALFORTORE WINDFARM

Ziel

To disseminate the WTGs in Puglia through the realization of 5 AIT 02 MK2 wind farm with 1600 kW of total electric power.

This wind farm is composed of 5 AIT 02 MK2 WTGs with 320 kW each, for a total installed power of 1600 kW. From Enel grid to each WTGs there are the following main components :
* Box of electric station MT/MT (medium voltage/medium voltage)
* Connection MT lines between station MT/MT and the WGTs boxes
* Boxes MT/BT (medium voltage/now voltage) placed near the WGTGs (one box per each WTG)
* Connection BT line between box MT/BT and WTG
* Moreover the wind farm includes as subsystem :
* Meaurement, Control, Monitoring station
* Anemometric - Meteorologic plant
The producibility of such a wind farm essentially depends on the site anemologic characteristics, that is on wind annual mean velocity and on site height above sea level.
Assuming at hub height (26 m from ground) an annual mean velocity 8.4 m/s (value found out by preliminary analyses in Roseto Valfortore area) this wind farm, with 100% availability, will produce 5.060.00 kWh in steady conditions.

Thema/Themen

Data not available

Aufforderung zur Vorschlagseinreichung

Data not available

Koordinator

Wind Energy System Taranto Alenia SpA West
EU-Beitrag
Keine Daten
Adresse
Via Ariosto 12 Zona Industriale
74100 Taranto
Italien

Auf der Karte ansehen

Gesamtkosten
Keine Daten