PJ27 started in November 2016 with planning activities in order to draft and agree a Demonstration Plan based on the Grant Agreement and based on a common IOP Roadmap that is shared with PJ18-02b. At the begin of December 2016, there was a meeting of the SESAR IOP Decision Team during which a revised IOP Roadmap was proposed by the Coflight members DSNA, ENAV, LEONARDO and THALES. Main reason for this proposal was that the IOP work planned in SESAR 1 programme needs to be finalised in SESAR 2020. PJ27 received an action from the IOP Decision Team to provide an updated Project Plan until March 31, 2017.
During a PJ27 PMB Meeting in January 2017, a revised IOP Roadmap was agreed. This new roadmap considered the changed dependencies between PJ27 and PJ18-02b and defined a completion of the PJ27 Shadow Mode Demonstration until the end of 2019. This was corresponding to a completion of the PJ18-02b IOPEXE1 validation exercise until the end of 2018, which was already 6 months later compared to the IOP Roadmap from the Grant Agreement.
In February 2017, the Project started to work on the requirements work packages needed for non-functional requirements, AIM SWIM Service Requirements and MET SWIM Service Requirements. Due to the decision to terminate PJ27, these work packages could not be completed.
During a Meeting of the IOP Analysis Team in March 2017, the IOP Roadmap was again updated due to the need to shift the PJ18-02b IOPEXE1 validation exercise by 4 months.
During a meeting of the SESAR Programme Committee at March 29, the PC tasked the projects PJ27 and PJ18-02b to propose a revised IOP Roadmap and revised Project Plans, which anticipate the new completion date for the IOP1EXE validation exercise end of April 2019. The PC granted up to 6 months more time for the completion of the PJ27 Demonstration. The revised Project Plans due date was end of May 2017, providing an extension of 2 months for the project planning phase.
At May 31 2017, PJ27 submitted an updated Demonstration Plan for SJU and IOP Decision Team review. The Demonstration Plan included an embedded Safety Plan and an embedded Security Plan. Together with the Demonstraion Plan all the required Ethics Plans were submitted.
At June 13, the IOP Decision Team reviewed the proposed IOP Roadmap together with the updated 18-02b Validation Plan and PJ27 Demonstration Plan. One conclusion from this review was to recommend to the Programme Committee PJ27 for termination, because the resource needs for 18-02b and PJ27 could not be covered anymore and higher priority was given to 18-02b.
At July 12, the Programme Committee reviewed the recommendations of the IOP Decision Team and decided to follow the recommendation for PJ27 Termination. The SJU Executive Director decided to coordinate with the EC before taking a final decision. PJ27 entered into an idle mode and awaiting the confirmation for termination from the SJU Executive Director.
At October 27 2017, the SJU Executive Director confirmed the PJ27 Termination by sending a pre-termination notification to the Project coordinator. The pre-termination was answered by PJ27 in December 2017.
At December 18, 2017 the SJU Executive Director send the Termination confirmation to the PJ27 Project coordinator. The Project Termination is effective at December 31, 2017.