MELTING OF RADIOACTIVE METAL SCRAP FROM THE KRB-A PLANT

Objective

RADIOACTIVITY HOMOGENISATION AND VOLUME COMPACTION OF LOW-LEVEL RADIOACTIVE SCRAP CAN BE ACHIEVED BY MELTING. THEN, DEPENDING ON THE AVERAGE SPECIFIC ACTIVITY, THE METAL CAN BE RELEASED IN GENERAL TO THE NUCLEAR MARKET, OR STORED FOR FINAL DISPOSAL. HOWEVER, MELTING IN STANDARD FOUNDRIES WITHOUT CONTROLLED CONTAINMENT ATMOSPHERE HAS TO BE LIMITED TO SCRAP WITH LOW SPECIFIC ACTIVITY (< 74 BQ/G ), AND LARGE-SCALE EXPERIENCE WITH MELTING OF HIGHER-LEVEL RADIOACTIVE METAL SCRAP IS PRESENTLY NOT AVAILABLE.

THE WORK PROGRAMME WAS, FOR TECHNICAL AND ECONOMIC REASONS, REVISED IN A SUPPLEMENTARY AGREEMENT CONCLUDED IN 1988, AFTER EXECUTION OF ITEMS B.1. TO B.2. THE REVISION AIMS AT GAINING EXPERIENCE BY LARGE-SCALE MELTING OF ABOUT 300 T OF METAL WASTE FROM THE KRB-A DECOMMISSIONING, WITH RADIOACTIVITY LEVELS UP TO 500 BQ/G. THE MELTING WILL BE PERFORMED IN AN INDUCTION FURNACE (CAPACITY CA. 3T) IN A CONTROLLED ZONE AT THE SITE OF SIEMPELKAMP GIESSEREI KREFELD (SRG), ACTING AS SUBCONTRACTOR, THE RADIOACTIVE WASTE BEING TRANSPORTED FROM KRB TO SRG.

THE STUDY IS EXPECTED TO RESULT IN A STATEMENT WHETHER THE ABOVE PROCEDURE HAS A POTENTIAL FOR LARGE-SCALE APPLICATION.

B.1. ASSESSMENT OF PROPOSALS FOR SERVICES FROM EXTERNAL CONTRACTORS, MAINLY CONCERNING THE LEASING OF AN INDUCTION MELTING FURNACE.
B.2. DEFINITION OF A WORK PROCEDURE, INCLUDING THE SELECTION OF REPRESENTATIVE COMPONENTS FOR MELTING TESTS AND OF APPROPRIATE TECHNIQUES FOR DECONTAMINATION,DISMOUTING AND CUTTING, THE DEFINITION OF A PROCEDURE FOR THE INSTALLATION AND OPERATION OF THE MELTING FURNACE, AND A PRELIMINARY PLANNING FOR HEALTH PHYSICS PROTECTION.
B.3. PREPARATION OF LICENSING PROCEDURES FOR THE INSTALLATION AND OPERATION OF A MELTING FURNACE ON THE SITE OF SRG/KREFELD.
B.4. EXECUTION OF THE MELTING PROGRAMME ON THE SITE OF SRG/KREFELD.
B.4.1. CONCEPTION AND CONSTRUCTION OF A FACILITY FOR THE MELTING OF METAL SCRAP UP TO 500 BQ/G.
B.4.2. STUDY INTO THE NUCLIDE DISTRIBUTION DURING MELTING OF CONTAMINATED AND ACTIVATED SCRAP.
B.4.3. NUCLIDE-SPECIFIC STUDY INTO ACTIVITY RELEASES DURING TWO SEQUENTIAL MELTING PROCESSES.
B.4.4. CASTING OF WASTE DISPOSAL PACKAGES CONTAINING HIGHER-LEVEL RADIOACTIVE (500 BQ/G) COMPONENTS EMBEDDED IN A MATRIX CAST OUT OF LOWER-LEVEL RADIOACTIVE SCRAP ("ONION PACKAGE").
B.4.5. MELTING OF SLAG AND SAWING CHIPS ARISING FROM DISMANTLING PROCESSES.
B.5. EVALUATION OF THE ABOVE MELTING PROCESSES ON THE BASIS OF LABORATORY ANALYSES AND CONCLUSIVE ASSESSMENT OF THE POTENTIAL FOR LARGE-SCALE APPLICATION.

Fields of science (EuroSciVoc)

CORDIS classifies projects with EuroSciVoc, a multilingual taxonomy of fields of science, through a semi-automatic process based on NLP techniques. See: The European Science Vocabulary.

You need to log in or register to use this function

Programme(s)

Multi-annual funding programmes that define the EU’s priorities for research and innovation.

Topic(s)

Calls for proposals are divided into topics. A topic defines a specific subject or area for which applicants can submit proposals. The description of a topic comprises its specific scope and the expected impact of the funded project.

Data not available

Call for proposal

Procedure for inviting applicants to submit project proposals, with the aim of receiving EU funding.

Data not available

Funding Scheme

Funding scheme (or “Type of Action”) inside a programme with common features. It specifies: the scope of what is funded; the reimbursement rate; specific evaluation criteria to qualify for funding; and the use of simplified forms of costs like lump sums.

CSC - Cost-sharing contracts

Coordinator

Kernkraftwerk RWE - Bayernwerk GmbH
EU contribution
No data
Address
1,Dr.-August-Weckesser-Strasse
89355 Gundremmingen
Germany

See on map

Total cost

The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.