Skip to main content
Go to the home page of the European Commission (opens in new window)
English English
CORDIS - EU research results
CORDIS
Content archived on 2024-05-14

25 kW GRID CONNECTED PV GENERATOR INTEGRATED INTO THE ELECTRICITY SUPPLY STRUCTURE

Objective

The main objective of this project is, at the European level, to demonstrate the advantages of an innovative grid connected photovoltaic (PV) installation, which offers an optimal solution to the following problems in the present energy supply structure :
- low energy efficiency due to losses in transport
- low energy efficiency due to losses in transformation processes
- institutional barriers to using purer technology
This solution will serve as a model for further diffusion of grid connected PV systems in Spain and in other European countries.

Has been determinated that the energy consumption of the Health Centre in Arnoia, where the solar system was installed, will always be more than the maximal theorical capacity of the Solar Generator production.
A delay in the Monitoring phase was made when connecting the line phone. It was due to the Spanish Phone Company (Telefonica). Nowadays the modem connection for the data acquisition equipment and the monitoring is concluded.
1. Innovative technology and context :
The main innovation of the project is found in the way the electricity is supplied to the local grid in low tension resulting in minimal losses from transformation and transport. The installation has been put in place and directly connected to the local grid with no adaptation necessary in it. As the electricity distribution corresponds with the local authority, who is a co-proposer of this project, no changes in normal procedures in the electricity distribution has been needed.
The production will serve as a supplement to the electricity bought and transformed by the electricity distributor, and as such a larger generator could be installed in the future. However, for demonstration purposes, and for generating the positive influence in the local society, a 25 kWp installation is sufficiently large to demonstrate the integration. 2. Economic aspects :
Expected annual production :25 kW x 1630 peak solar hours per year = 29150 kWh/y.
In 1994, Ayto. de Arnoia bought 1294 MWh from Union-Fernosa and paid 12955000 PTA. Ayto. de Arnoia estimates losses in transformation of 82 MWh and a study done by Albasolar says 97 MWh. This gives an effective price after transformation of 10,7 PTA/kWh.
The effective price of electricity paid by the end-users in Ayto. de Arnoia was approximately 28PTA. A prudent estimation of the real cost by Ayto.de Arnoia (taking into account the depreciation of transformers and the cost of maintenance and operation) is 14 PTA/kWh. The minimum monetary value of the energy produced will therefore be : E= 14PTA x 29150 kWh/y = 408100PTA/Y
The expected pay-back is 119,7 years.
3. Monitoring : Monitoring phase ongoing

Fields of science (EuroSciVoc)

CORDIS classifies projects with EuroSciVoc, a multilingual taxonomy of fields of science, through a semi-automatic process based on NLP techniques. See: The European Science Vocabulary.

You need to log in or register to use this function

Programme(s)

Multi-annual funding programmes that define the EU’s priorities for research and innovation.

Topic(s)

Calls for proposals are divided into topics. A topic defines a specific subject or area for which applicants can submit proposals. The description of a topic comprises its specific scope and the expected impact of the funded project.

Call for proposal

Procedure for inviting applicants to submit project proposals, with the aim of receiving EU funding.

Data not available

Funding Scheme

Funding scheme (or “Type of Action”) inside a programme with common features. It specifies: the scope of what is funded; the reimbursement rate; specific evaluation criteria to qualify for funding; and the use of simplified forms of costs like lump sums.

DEM - Demonstration contracts

Coordinator

ALBASOLAR SL
EU contribution
No data
Address
RDA. DE LA BUGANVILLA DEL REY 78
28023 Madrid
Spain

See on map

Total cost

The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.

No data
My booklet 0 0