Project description
Intelligent adaptive storage to boost high-performance computing
The growing need to process extremely large data sets is the driving force accelerating the transition to high-performance computing. However, the flat data storage hierarchies with a central parallel file system are proving to be inadequate. Emerging multi-tier storage hierarchies could meet the needs of data-intensive applications but currently lack adequate control mechanisms for the available resources. The EU-funded ADMIRE project plans to develop an adaptive storage system that should allow high-performance computing systems to deliver very high throughput and increase application performance. The aim is to significantly improve the runtime of applications in fields such as weather forecasting, remote sensing and deep learning.
Objective
The growing need to process extremely large data sets is one of the main drivers for building exascale HPC systems today. However, the flat storage hierarchies found in classic HPC architectures no longer satisfy the performance requirements of data-processing applications. Uncoordinated file access in combination with limited bandwidth make the centralised back-end parallel file system a serious bottleneck. At the same time, emerging multi-tier storage hierarchies come with the potential to remove this barrier. But maximising performance still requires careful control to avoid congestion and balance computational with storage performance. Unfortunately, appropriate interfaces and policies for managing such an enhanced I/O stack are still lacking.
The main objective of the ADMIRE project is to establish this control by creating an active I/O stack that dynamically adjusts computation and storage requirements through intelligent global coordination, malleability of computation and I/O, and the scheduling of storage resources along all levels of the storage hierarchy. To achieve this, we will develop a software-defined framework based on the principles of scalable monitoring and control, separated control and data paths, and the orchestration of key system components and applications through embedded control points.
Our software-only solution will allow the throughput of HPC systems and the performance of individual applications to be substantially increased – and consequently energy consumption to be decreased – by taking advantage of fast and power-efficient node-local storage tiers using novel, European ad-hoc storage systems and in-transit/in-situ processing facilities. Furthermore, our enhanced I/O stack will offer quality-of-service (QoS) and resilience. An integrated and operational prototype will be validated with several use cases from various domains, including climate/weather, life sciences, physics, remote sensing, and deep learning.
Keywords
Project’s keywords as indicated by the project coordinator. Not to be confused with the EuroSciVoc taxonomy (Fields of science)
Project’s keywords as indicated by the project coordinator. Not to be confused with the EuroSciVoc taxonomy (Fields of science)
Programme(s)
Multi-annual funding programmes that define the EU’s priorities for research and innovation.
Multi-annual funding programmes that define the EU’s priorities for research and innovation.
-
H2020-EU.2.1.1. - INDUSTRIAL LEADERSHIP - Leadership in enabling and industrial technologies - Information and Communication Technologies (ICT)
MAIN PROGRAMME
See all projects funded under this programme -
H2020-EU.2.1.1.2. - Next generation computing: Advanced and secure computing systems and technologies, including cloud computing
See all projects funded under this programme
Topic(s)
Calls for proposals are divided into topics. A topic defines a specific subject or area for which applicants can submit proposals. The description of a topic comprises its specific scope and the expected impact of the funded project.
Calls for proposals are divided into topics. A topic defines a specific subject or area for which applicants can submit proposals. The description of a topic comprises its specific scope and the expected impact of the funded project.
Funding Scheme
Funding scheme (or “Type of Action”) inside a programme with common features. It specifies: the scope of what is funded; the reimbursement rate; specific evaluation criteria to qualify for funding; and the use of simplified forms of costs like lump sums.
Funding scheme (or “Type of Action”) inside a programme with common features. It specifies: the scope of what is funded; the reimbursement rate; specific evaluation criteria to qualify for funding; and the use of simplified forms of costs like lump sums.
RIA - Research and Innovation action
See all projects funded under this funding scheme
Call for proposal
Procedure for inviting applicants to submit project proposals, with the aim of receiving EU funding.
Procedure for inviting applicants to submit project proposals, with the aim of receiving EU funding.
(opens in new window) H2020-JTI-EuroHPC-2019-1
See all projects funded under this callCoordinator
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
28903 Getafe (Madrid)
Spain
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Participants (18)
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
55122 MAINZ
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
08034 Barcelona
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
64289 Darmstadt
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
92360 Meudon La Foret
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
78153 Le Chesnay Cedex
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
33000 Bordeaux
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
91680 Bruyeres Le Chatel
See on map
The organization defined itself as SME (small and medium-sized enterprise) at the time the Grant Agreement was signed.
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
52428 JULICH
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
00185 ROMA
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
80133 Napoli
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
10124 TORINO
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
56126 PISA
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
20122 Milano
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
40033 Casalecchio Di Reno Bo
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
42019 SCANDIANO
See on map
The organization defined itself as SME (small and medium-sized enterprise) at the time the Grant Agreement was signed.
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
61-704 POZNAN
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
100 44 Stockholm
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.
Net EU financial contribution. The sum of money that the participant receives, deducted by the EU contribution to its linked third party. It considers the distribution of the EU financial contribution between direct beneficiaries of the project and other types of participants, like third-party participants.
80539 Munchen
See on map
The total costs incurred by this organisation to participate in the project, including direct and indirect costs. This amount is a subset of the overall project budget.