Final Cost-Benefit Analysis (CBA)
(opens in new window)
The cost-benefit analysis (CBA) documents the potential benefits, when deployed in the applicable environments and whether or not they are expected to exceed the costs over a given time horizon
Final Contextual Note
(opens in new window)
"The contextual note provides to any interested reader, external and internal to the SESAR programme, an introduction to the ""Triangle Architecture with Cyber-resilience"" solution in terms of scope, main operational and performance benefits as well as relevant system impacts, etc. It also contains recommendations regarding additional activities to be conducted during the industrialization phase or as part of deployment. It introduces the technical data pack comprising the SESAR 3 JU"
Final Technical Validation Report (TVALR)
(opens in new window)
"The Technical Validation Report consolidates the validation results of the different validation exercises which will be performed in the framework of the ""Triangle Architecture with Cyber-resilience"" solution, once the validation activities have been completed."
Final Communication, Dissemination and Exploitation Plan (CDE)
(opens in new window)
The Plan for communication, dissemination and exploitation activities (CDE) shall report on all communication and dissemination activities performed during the course of the project, but also to consolidate all exploitation activities to be completed after the closure of the project
Intermediate Communication, Dissemination and Exploitation Plan (CDE)
(opens in new window)
The Plan for communication, dissemination and exploitation activities (CDE) shall report on all communication and dissemination activities performed during the course of the project, but also to consolidate all exploitation activities to be completed after the closure of the project
Final Technical Specification and Interface Requirement Specification (TS/IRS)
(opens in new window)
"The TS/IRS document provides the functional, non-functional and interface equirements related to the ""Triangle Architecture with Cyber-resilience"" solution. The technical specifications address the “what” and not the “how”, they aim at specifying the functional description and the necessary logical interfaces among ADSPs and other parts of the ATM system"
Initial Communication, Dissemination and Exploitation Plan (CDE)
(opens in new window)
The Plan for communication, dissemination and exploitation activities (CDE) shall report on all communication and dissemination activities performed during the course of the project, but also to consolidate all exploitation activities to be completed after the closure of the project
Final REG
(opens in new window)
The Regulatory deliverable proposes SESAR acceptable means of compliance to EASA to illustrate means to establish compliance with the Single European Sky basic regulation and its implementing rules.
Final STAND
(opens in new window)
The Standardisation deliverable (STAND) documents propose the SESAR input to standardisation activities (e.g. EUROCAE).