a. Technical work linked to objective 1.
The technical work to be carried out to achieve objective 1 is included in WP 1. WP 1 is completed (deliverable D1.1 has been approved with some minor comments by SJU and re-submitted, D1.2 has been submitted; (MS-4 achieved upon approval of D1.2). Tasks 1.1 Task 1.2 and Task 1.3 have been completed. Therefore, the target achievement is 100%. See overall assessment in Section 1.2.1.
b. Technical work linked to objective 2.
The technical work to be carried out to achieve objective 2 is included in WP 2. WP 2 is in progress (deliverables D2.1 and D2.2 have been approved by SJU). Tasks 2.1 and Task 2.2 have been completed. Task 2.3 is 50% fulfilled; Task 2.4 is 30% fulfilled. Hence, the achievement of the objective is at 70 %. Risk 5 is active. See overall assessment in Section 1.2.2.
c. Technical work linked to objective 3.
The technical work to be carried out to achieve objective 3 is included in WP 3. WP 3 is in progress (deliverable D3.1 has been approved by SJU). Task 3.1 is at 100% fulfilled, Task 3.2 at 10% fulfilled, and Task 3.3 at 0% fulfilled. Consequently, the achievement of the objective is at 50%. See overall assessment in Section 1.2.3.
d. Technical work linked to objective 4.
The technical work to be carried out to achieve objective 4 is included in WP 4. WP 4 is in progress (deliverable D4.1 and D4.2 has been submitted). Task 4.1 is completed at 80% fulfilled. Task 4.2 is completed at 10%. Task 4.3 is at 5%. All in all, the achievement of the objective is at 40%. See overall assessment in Section 1.2.4
Project achievement (overall assessment)
At the end of this 1st Reporting Period, the overall achievement can be set at about 40%.
Due to the delay in receiving the MTG data, some of the objectives have been delayed beyond expectations. Objectives described above are progressing at good pace:
• Objective 1 – WP1 is at 100% fulfilled.
• Objective 2 – WP2 is at 70% fulfilled.
• Objective 3 – WP4 is at 50% fulfilled.
• Objective 4 – WP5 is at 40% fulfilled.