Periodic Reporting for period 1 - NextFuel (Industrialising eSMR to Supply the Next Shipping Fuels)
Période du rapport: 2023-12-01 au 2025-02-28
The project will enable production of renewable methanol from using our eSMR approach, to enable a cost closer to the fossil alternative, and to study how this approach can be successfully scaled. The project’s impact is significant towards supporting EU’s ambitious targets to cut emissions in the maritime sector.
One of our main objectives is to provide an ecosystem simulation platform that predicts energy efficiency (using the demonstrator as the case) with +80% accuracy, by combining process simulations (by TOPSOE), resource simulations (by NTNU) and value chain simulations (by CERTH), utilising the industrial know-how while we bring state-of-the-art simulation approaches to methanol production (and its ecosystem). Another objective is to improve carbon efficiency from present 40% of fossil derived methanol defining a pathway to +90% carbon efficiency.
We develop the project in three phases. In the first we develop the generic models. This covers frameworks to agree to model information relevant to biomethanol plant sizes and requirements, which in turn is built on information in areas such as environmental impact, cost impact, feedstock availability, logistics solutions and more. This is then used to build simulation models of plants and ecosystems, focusing on key unsolved areas such as energy integration with the biogas plant as well as hydrogen integration. Both of these feed into the plant design, where the size is also set and next the detailed design. We target copy-paste plant designs, as design is a substantial part of cost. From the plant design we get the key process-module of the eSMR technology, which is then shipped to the next step. Here we demonstrate an operational plant, and both validate our approaches (including the world’s first industrial pilot of eSMR and the biogas-eSMR integration). All the project experience is next used in developing the tools to configure plants and value chains, that are then tested on conceptual designs (covering business models, environmental impact and more) for different plant sizes (including considerable scale-ups from the demonstrator plant).
Established a modelling framework in Aspen Plus following a literature review and definition of a preliminary base case. Process simulations were carried out for multiple feedstock scenarios (biomethane, biogas, CO2), including flexible stoichiometry adjustment. Sensitivity analyses and scenario studies were conducted to optimise operating conditions and process configurations. Renewable power demand, hydrogen and syngas balances, utility requirements, energy efficiency and carbon utilisation were quantified to support downstream engineering work.
WP4 - Plant Design & Optimization
The 150 MTPD biomethanol plant was developed from feasibility study through Design Basis, BEDP and FEED. The Design Basis defined technical, operational, safety and regulatory boundary conditions. Engineering activities included development of PFDs and P&IDs, equipment sizing and specifications, control and safety system definition (including preliminary HAZOP inputs), electrical design, budget estimation, and preparation of a 30% 3D model. Parallel site preparation activities addressed permitting, grid connection, feedstock and offtake agreements, financing dialogue, and integration with the selected EPC contractor.
WP5 - Data & Demonstration
The FEED documentation was consolidated into an overall EPC contracting and execution model together with the selected EPC contractor. Project structuring, risk allocation principles and procurement planning frameworks were developed to prepare the transition from engineering to construction.
Main achievements
• Completion of advanced process simulations enabling a flexible and robust plant concept capable of operating on a wide range of feedstocks.
• Quantification of energy balances, renewable power demand and carbon utilisation, providing validated input for plant design and impact assessment.
• Delivery of the full Design Basis, BEDP and FEED for the 150 MTPD plant, including several hundred engineering documents and a 30% 3D model.
• Technical validation of the eREACT-based biomethanol process as design-ready and suitable for industrial implementation.
• Establishment of a firm bid basis for core plant modules and development of an EPC contracting and procurement framework.
• Significant reduction of technical and implementation risks, positioning the project for Final Investment Decision (FID) and transition to construction in the next reporting period.