2.3.2016 kick of meeting, FS, place SK-Velky Slavkov,
During the period from March to July 2016, we monitored the amount of filtered water per m²/h reflecting membrane permeability
Task 2, A - Intake: 16 samples were taken and 112 analyses in the following parameters were made
Task 2, B - Biological process: 96 samples were taken and 96 analyses were made:
Task 2, C - MBR module, 814 samples were taken and 814 analyses were made with the following result (figure 3)
Task 2, D - Outflow, 32 samples were taken and 192 analyses were made (figure 3)
Task 2, E – Designing technological scheme, Based on the obtained data the design department elaborated proposals for type series in three versions:
1) internal version up to 250 PE (all-in-one)
2) external version – container up to 1500 PE (ext_container)
3) external version (ext_membrane dispatch into concrete)
Task 2, F – Design of the automatic management system (ASRTP) and Task 2, G – Software design
We finalized the management of the membrane module, which created a design for control system (hereinafter ASRTP), which we plan to deploy in electrical switchboards of the WWTP.
During April to Jun 2016 we carried out the market analysis in the following steps:
1- Market research and survey of customer (sending questionnaires via email/post and evaluation).
2- Price analysis and pricing policy - total cost, the end price for the customer, determining the lifecycle
3- Analysis of competitors, implemented similar and alternative solutions. Their comparison with us, specification of the Value Proposition, clarification of the competitive advantage, specification of the target group for market entry and update of the Business Model.
Finally in the august, we processed the SWOT and assessed the risks to the project implementation.
In the august we perform finnal study evaluation a prepare draft plan for implementation of the phase II.
Based on the new findings obtained from the study, in terms of its evaluation and conclusions, we want to implement a project that will fulfil our long-term strategy, move the innovation of the WWTP into the phase TRL8 and prepare it for its introduction on the market. We have designed a size type line and for us to verify the results achieved, we chose to implement the following WWTP sizes for implementation in phase 2:
1) all-in-one, BCTS15, 250 PE, 15 m³/d
2) ext_container, BCTS240, 1500 PE, 240 m³/d
3) ext_membrane dispatch_in_concrete, BCTS2500EXTDP, 2500 PE, 375 m³/d
We determined dimensions, technical conditions for the implementation, the management system and two-way transfer of data for the WWTP management from the centre. We would like to implement these reference WWTPs in phase 2. Implementation means that on the basis of their technical documentation, we will manufacture, install and operate them for a particular client in order to confirm the results we have achieved in the phase 1.