H2H project kick-off performed on 8/12-2017 and the project finished on 31/5-2021.
H2H web-site has been established:
https://www.sintef.no/projectweb/hull-to-hull/(opens in new window). The website has been maintained and updated with progress during the project.
Project administration set up, with data storage, reporting templates and document templates.
All deliverables have been reviewed and approved. The H2H concept has been elaborated and consolidated, and reflected concept description and system requirements. This basis, together with demonstration planning, has lead to the definition of in pilot system requirements and requirements for safe and secure communications. A preliminary business plan has been prepared, which will be finalized for final review after second period.
For the final period all project deliverables have been reviewed and approved.
A main outcome of the project was the three demonstrations that were run as online events, demonstrating live use of the H2H concept in the different use cases:
* simultaneous operation with two vessels working together
* auto-mooring operation with an inland waterways vessel auto-mooring to a quay
* inland waterways docking and straight sailing.
During the final reporting period, the following activities have been carried out:
Dissemination:
1. Continuously update of the project website:
https://www.sintef.no/projectweb/hull-to-hull/(opens in new window) 1. 2nd project flyer distributed at the 2nd ICMASS conference in Trondheim 2019.
2. 11 papers/publications from SINTEF Ocean, SINTEF Digital (SINTEF AS) and KU Leuven. A detailed list of publications is found in Deliverable D9.2 Dissemination material.
The deliverable D9.2 Dissemination material covers disclosure of the project results on the web, presentation at conferences and publications in conference proceedings and scientific journals.
Communication (workshop and media engagement)
The communication activities are reporting in two deliverables D9.3 Yearly workshops and D9.4 Media engagement.
Yearly workshops:
• During the last reporting period we manage to have 2 internal workshops before the pandemic. Both were arranged in 2019 in combination with relevant conference and workshop.
• There have been none internal workshops in 2020 and 2021.
Symposium:
• The project has been presented at two different symposia related to autonomous inland shipping and autonomous ship.
Targeting regulatory bodies/standards:
• IHO Data Quality Working Group has proposed to include the uncertainty zone concept into S-100 Standard/Framework
All these 3 main communication activities are covered in deliverable D9.3 Yearly workshop.
Media engagement:
The project has been promoted in different social media as LinkedIn and webinars related to the 3 demonstrations and a separate webinar on maritime 5G. There have been none physical meetings since 2019 due to the pandemic.
The media engagement activities are covered in deliverable D9.4 Media Engagement.
Both deliverables D9.3 and D9.4 covers the main activities for two-ways interaction with different stakeholders within autonomous navigation.
Exploitation of project results:
Exploitation activities after project's lifecycle are covered in deliverable D9.5 Plan for Exploitation after Project Finished.