The Haeolus project will install a 2.5 MW electrolyser in the remote region of Varanger, Norway, inside the Raggovidda wind farm, whose growth is limited by grid bottlenecks.
The electrolyser will be based on PEM technology and will be integrated with the wind farm, hydrogen storage and a smaller fuel cell for re-electrification.
To maximise relevance to wind farms across the EU and the world, the plant will be operated in multiple emulated configurations (energy storage, mini-grid, fuel production).
Like many large wind farms, especially offshore, Raggovidda is difficult to access, in particular in winter: Haeolus will therefore deploy a remote monitoring and control system allowing the system to operate without personnel on site.
Maintenance requirements will be minimised by a specially developed diagnostic and prognostic system for the electrolyser and BoP systems.
The containerised electrolyser is a standard model carried by project partner Hydrogenics. The integrated system will be housed in a specially erected hall to protect it from the Arctic winter and allow year-round access. The integrated system of electrolyser, fuel cells, and wind farm will be designed for flexibility in demonstration, to allow emulating different operating modes and grid services.
Haeolus answers the AWP's challenge with the widest possible project scope, with operation modes not limited to the site's particular needs but extended to all major use cases, and several in-depth analyses (released as public reports) on the business case of electrolysers in wind farms, their impact on energy systems and the environment, and their applicability in a wide range of conditions.
Fields of science
Keywords
Programme(s)
- H2020-EU.3.3. - SOCIETAL CHALLENGES - Secure, clean and efficient energy Main Programme
- H2020-EU.3.3.8.2. - Increase the energy efficiency of production of hydrogen mainly from water electrolysis and renewable sources while reducing operating and capital costs, so that the combined system of the hydrogen production and the conversion using the fuel cell system can compete with the alternatives for electricity production available on the market
- H2020-EU.3.3.8.3. - Demonstrate on a large scale the feasibility of using hydrogen to support integration of renewable energy sources into the energy systems, including through its use as a competitive energy storage medium for electricity produced from renewable energy sources
Funding Scheme
IA - Innovation actionCoordinator
7034 Trondheim
Norway
See on map
Participants (16)
25000 Besancon
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
90400 Sevenans
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
25000 Besancon
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
25030 Besancon Cedex
See on map
20009 DONOSTIA-SAN SEBASTIAN (GIPUZKOA)
See on map
82100 Benevento
See on map
9815 Vadso
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
9800 Vadso
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
9815 Vadso
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
9800 Vadso
See on map
The organization defined itself as SME (small and medium-sized enterprise) at the time the Grant Agreement was signed.
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
9815 Vadso
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
9800 Vadso
See on map
Legal entity other than a subcontractor which is affiliated or legally linked to a participant. The entity carries out work under the conditions laid down in the Grant Agreement, supplies goods or provides services for the action, but did not sign the Grant Agreement. A third party abides by the rules applicable to its related participant under the Grant Agreement with regard to eligibility of costs and control of expenditure.
9800 Vadso
See on map
Participation ended
82100 Benevento
See on map
The organization defined itself as SME (small and medium-sized enterprise) at the time the Grant Agreement was signed.
Participation ended
7034 Trondheim
See on map
2260 Westerlo
See on map
The organization defined itself as SME (small and medium-sized enterprise) at the time the Grant Agreement was signed.