This is the work carried out during the period covered by the report:
* In WP1 the definition of the the technical, social, and environmental requirements of future wind turbines (2030-2050) and for the design tools and methodology to be developed within the project were carried out. The definitive concepts and pre-designs of the three case studies were also defined as well. The new pitch bearing (CS1) and gearbox concepts (CS2) for large wind turbines were predefined. The requirements needed for lifetime extension were also obtained analysing an innovative pitch bearing lifetime extension concept (CS3).
* In WP2 (Advanced virtual testing anf design tools for ensuring reliability): In this period the methodology to evaluate the variability on loading conditions in a farm between wind turbines is fully developed. The methodology for the induction hardening process applied to the raceway of the CS1 pitch bearing is also finished. The methodologies related virtual sensing are also developed.
* In WP3 (Simplified tailored physical testing):There are no finalized tasks, but in most of the tasks the tests are already started and first tested specimens are already obtained: flat and cylindrical samples under RCF, rolling element failure analysis, adhesive property evaluation, etc. Test concept on laboratory scale journal bearing tests are in the definition phase.
* In WP6 (Environmental, social and economic assessment): The objective of WP6 is to assess the environmental, social and economic life cycle impacts and to show the environmental, social and economic benefits of the project solutions. A three-part sustainability assessment will be performed – i.e. an environmental life cycle assessment (LCA), social life cycle assessment (S-LCA) and life cycle costing (LCC) – iteratively throughout the project in close interaction with the previous WPs. During the period covered, the definition and assestment of the BAU reference scenarios per case study was finalized.
* In WP7, the communication and dissemination plans was defined. A Stakeholder Working Group was created (currently formed by expert representatives of DNV-GL, GE, IBERDROLA, LORC, SIEMENS GAMESA, ORE CATAPULT, SIRRIS and VESTA) to assure the highest potential for innovation and market uptake for all activities during INNTERESTING. Communication and dissemination material to promote the project´s activities were developed.