Objetivo
The object of the underlying work programme is the dismantling of the B205 Fuel Reprocessing Pilot Plant. The plant was operated from 1957 to 1965. It processed uranium metal, totalling several hundred kilograms of fuel (typically 4,000 MWD/te). The product purification, solvent wash and sampling facilities were dismantled in the early 1970's leaving the MA cell nearly empty and the suite of HA cells untouched.
The aim of the project is to remove all of the contaminated structures from the laboratory (including the plinths that the cells are standing upon). It is ultimately intended to reuse the laboratory. This project will be used as a development project to demonstrate the techniques for dismantling this type of facility.
The contract covers dismantling work of the New Dissolver Cell, of the original HA Cell and of the Metal Cutting Cell. Information on the dismantling of the MA Cell (working period: August 1991 - March 1992) and of the New Primary Separation Cell (working period: July 1994 -September 1995 ) will be made available to the CEC.
This decommissioning project provides scope for testing a full range of techniques: for visual/radiometric inspection; remote handling; containment and shielding; decontamination of stainless steel, lead, concrete/brickwork; waste categorization, segregation, monitoring and size reduction. Residual metal fuel, fuel cladding and historic dissolver liquor spillages provide authentic decontamination problems.
Estimated mean dose rates vary between less than 1E-2 mSv/h for the laboratory and 200 mSv/h for the cutting cell with hot spots in the latter area of up to 470 mSv/h.
Lessons to be learnt include operational effectiveness, reliability, "user-friendliness", secondary waste arisings, manpower needs, dose-uptake, etc. The data sought is fundamental to the evaluation of future large-scale decommissioning projects and invaluable feedback into technique development programmes. It is planned to effect industrial-scale evaluation of decommissioning techniques, thereby providing data to assist planning, cost estimation and implementation of subsequent major projects.
The work programme will complement, and involve cooperation with the parallel Danish project at Riso National Laboratory.
The aim of the project is to remove all of the contaminated structures from the laboratory (including the plinths that the cells are standing upon). It is ultimately intended to reuse the laboratory. This project will be used as a development project to demonstrate the techniques for dismantling this type of facility.
The removal and decontamination of redundant service lines, shielded liquor transfer line, fame hoods, internal walls, etc was carried out.
During demolition of the medium active cell additional contaminated vessels, pipework and lead shield material was uncovered which increased the volume of alpha contaminated waste and significantly increased the demolition programme timescale.
A design specification for remote handling equipment, maintenance facilities, containment structures and waste export equipment was prepared and issued for competitive tender.
To date waste metals were decontaminated and disposed as low level waste (LLW) or sent for recovery at Sellafield's own lead recovery facilities. Nondecontaminable material were consigned as LLW or plutonium contaminated material (PCM) if above the LLW disposal criteria.
Dose uptake levels for demolition of the medium active cell have been relatively low, in the region of 1 milli-sievert/man month.
WORK PROGRAMME
1. Preparatory work including assessment and/or backfitting and installation of auxiliary equipment and access routes.
1.1. Removal and decontamination of redundant service lines, shielded liquor transfer line, fume hoods, internal wall etc.
1.2. Refurbishment of the cell ventilation/filtration system,
1.3. Establishment of waste decontamination facilities,
1.4. Establishment of waste handling/export facilities for LLW, ILW and PCM waste,
1.5. Installation of new lifting beams to support manipulators and of other new equipment where required.
2. Dismantling of the New Dissolver Cell
2.1. Installation and commissioning of the manipulator
2.2. Removal of all supplementary shielding as far as possible and construction of a modular containment for working area and manipulator maintenance area.
2.3. Removal of concrete panels and dismantling of the inner stainless steel skin by using the manipulator
2.4. Removal of all process plant equipment and the remainder of the cladding, .SP 0 2.5. Clean-up/scabbling of all inside faces of the cell using the manipulator,
2.6. Removal of the remaining structure.
3. Dismantling of the Original High Active Cell
3.1. Installation and commissioning of the manipulator
3.2. Removal of all supplementary shielding as far as possible and construction of reusable modular containment, backed by lead brick as necessary, to form a working area and manipulator
3.3. Installation of waste handling arrangements,
3.4. Use of the manipulator to breach the lead brick wall and gain access,
3.5. Retrieval of the existing hoist from the cell to the maintenance area to be removed manually,
3.6. Dismantling and removal of all process plant using the manipulator,
3.7. Clean-up/scabbling of inside faces using the manipulator,
3.8. Removal of remaining walls and plinth.
4. Dismantling of the Metal Cutting Cell
5. Generation of specific data
Ámbito científico (EuroSciVoc)
CORDIS clasifica los proyectos con EuroSciVoc, una taxonomía plurilingüe de ámbitos científicos, mediante un proceso semiautomático basado en técnicas de procesamiento del lenguaje natural. Véas: El vocabulario científico europeo..
CORDIS clasifica los proyectos con EuroSciVoc, una taxonomía plurilingüe de ámbitos científicos, mediante un proceso semiautomático basado en técnicas de procesamiento del lenguaje natural. Véas: El vocabulario científico europeo..
Para utilizar esta función, debe iniciar sesión o registrarse
Programa(s)
Programas de financiación plurianuales que definen las prioridades de la UE en materia de investigación e innovación.
Programas de financiación plurianuales que definen las prioridades de la UE en materia de investigación e innovación.
Tema(s)
Las convocatorias de propuestas se dividen en temas. Un tema define una materia o área específica para la que los solicitantes pueden presentar propuestas. La descripción de un tema comprende su alcance específico y la repercusión prevista del proyecto financiado.
Las convocatorias de propuestas se dividen en temas. Un tema define una materia o área específica para la que los solicitantes pueden presentar propuestas. La descripción de un tema comprende su alcance específico y la repercusión prevista del proyecto financiado.
Convocatoria de propuestas
Procedimiento para invitar a los solicitantes a presentar propuestas de proyectos con el objetivo de obtener financiación de la UE.
Datos no disponibles
Procedimiento para invitar a los solicitantes a presentar propuestas de proyectos con el objetivo de obtener financiación de la UE.
Régimen de financiación
Régimen de financiación (o «Tipo de acción») dentro de un programa con características comunes. Especifica: el alcance de lo que se financia; el porcentaje de reembolso; los criterios específicos de evaluación para optar a la financiación; y el uso de formas simplificadas de costes como los importes a tanto alzado.
Régimen de financiación (o «Tipo de acción») dentro de un programa con características comunes. Especifica: el alcance de lo que se financia; el porcentaje de reembolso; los criterios específicos de evaluación para optar a la financiación; y el uso de formas simplificadas de costes como los importes a tanto alzado.
Coordinador
WA3 6AS WARRINGTON
Reino Unido
Los costes totales en que ha incurrido esta organización para participar en el proyecto, incluidos los costes directos e indirectos. Este importe es un subconjunto del presupuesto total del proyecto.