Objectif
3 Francis open-flume turbines which are no longer able to be renovated are to be replaced by innovatively arranged S-tube turbines with an installation position turned through 180 deg. at the Ingelfingen small hydroelectric power station. This will increase the annual output from the figure of 3000 MWh to date to approx. 4000 MWh and will ensure this output in the long term.
The S arrangement will minimize the modifications necessary to the actual structure which will mean very economical conversion costs. One turbine is to be double-regulated and variable-speed. The other will be simply impeller-adjustable and frequency-variable.
In order to improve environmental acceptability, both turbines in the section coming into contact with water are to be equipped with oil-free, selb-lubricating or water-lubricated bearings. This will thus exclude the possibility of contamination of the works water.
It has been possible to achieve the main objectives of rebuilding at the Ingelfingen power station.
- The planned increase in annual production to 4 m kWh was almost achieved with 3.7 m kWh (before rebuilding approx. 3 m kWh)
- The innovative technologies introduced are working satisfactorily for the most part. Only the water-lubricated downstream had to be reequipped on account of sealing problems between the water lubrication and works water.
- The double regulated Kaplan n?2 turbine exceeded design data as regards absorption capacity and output. Instead of the planned terminal output of 378 kW, 404 KW was achieved.
- The idea of the solely impeller-regulated turbine with variable speed was not successful. It did not result in the outputs expected. The cause of this is to be identified as due to losses arising from infavourable flow characteristics in the partial load range and during excess opening could not be compensated for by variable speed since the quantity of water also changed as the speed changed, thus working against the control circuit.
The three existing Francis twin turbines are to be removed. It is planned to leave the old generators and mechanical turbine governors at their present positions. This will preserve the old, historically important internal and external appearance of the power station.
Demolition of the ceiling between the old intake chamber and aft-bay chamber with extension of the old suction pipes. Preparation for installation of the new intake pipes made of steel.
2 installation openings are to be made in the old aft-bay chamber ceiling for installation of the new turbines at the aft-bay side of the powerhouse in the powerhouse floor.
The aft-bay chamber and the tail water are to be deepened in line with the requirements of the new turbine, whereby the old powerhouse foundations will need to be underpinned in some cases.
Installation of 2 new concrete suction pipes and preparation or readying of the aft-bay chambers for installation of the new turbines. Extension of the powerhouse staircase down to the bed of the aft-bay chamber = new turbine house floor.
The innovative part of the project is based on the following special solutions :
* S-tube turbines with an installation position turned through 180 deg.
* The impeller hubs which have been oil-filled on tube turbines to date are to be converted to water lubrication.
* Lubricated front guide bearings made of plastic water elements.
* Oil-free wicket-gate-bearings made of sintered bronze with graphite inclusions.
* Turbine 1 desined by variable speed which disperses speed increaser.
Turbine 2 is desined with classical governing for Kaplan-turbines.
Technical datas :
Number of turbines : 2
Turbine typ : Turbine 1 Turbine 2
s-tube propeller s-tube turbine
governing by governing for
variable speed which Kaplan turbines
dispenses speed increaser
Max. turbine
Discharge :7,2 m3/s 7,2 m3/s
Max. capacity 368 kW 368 kW
Max. efficiency
(l/l) 90,5% 90%
Gross head : 6,06 m
Net head : 5,80 m
Extended annual energy production : 3967 MWh
Installation of the turbine casing with intake tube and suction pipe connection fitting, in addition to transmission. After completion of the turbine assembly, control and switch cabinets there will be a dry control run of the system is to be conducted with subsequent initial water filling and step-by-step start-up of the turbines at no load and then under load followed by switch-off operations: emergency trip/turbine trip/load shedding etc. After commissioning, all parties to the contract are to jointly conduct efficiency measurements on both turbines and a comparative appraisal between the two control modes of the turbine. During a 1-2 year operating phase, water ducting is to be recorded.
Champ scientifique (EuroSciVoc)
CORDIS classe les projets avec EuroSciVoc, une taxonomie multilingue des domaines scientifiques, grâce à un processus semi-automatique basé sur des techniques TLN. Voir: Le vocabulaire scientifique européen.
CORDIS classe les projets avec EuroSciVoc, une taxonomie multilingue des domaines scientifiques, grâce à un processus semi-automatique basé sur des techniques TLN. Voir: Le vocabulaire scientifique européen.
Ce projet n'a pas encore été classé par EuroSciVoc.
Proposez les domaines scientifiques qui vous semblent les plus pertinents et aidez-nous à améliorer notre service de classification.
Vous devez vous identifier ou vous inscrire pour utiliser cette fonction
Programme(s)
Programmes de financement pluriannuels qui définissent les priorités de l’UE en matière de recherche et d’innovation.
Programmes de financement pluriannuels qui définissent les priorités de l’UE en matière de recherche et d’innovation.
Thème(s)
Les appels à propositions sont divisés en thèmes. Un thème définit un sujet ou un domaine spécifique dans le cadre duquel les candidats peuvent soumettre des propositions. La description d’un thème comprend sa portée spécifique et l’impact attendu du projet financé.
Données non disponibles
Les appels à propositions sont divisés en thèmes. Un thème définit un sujet ou un domaine spécifique dans le cadre duquel les candidats peuvent soumettre des propositions. La description d’un thème comprend sa portée spécifique et l’impact attendu du projet financé.
Appel à propositions
Procédure par laquelle les candidats sont invités à soumettre des propositions de projet en vue de bénéficier d’un financement de l’UE.
Données non disponibles
Procédure par laquelle les candidats sont invités à soumettre des propositions de projet en vue de bénéficier d’un financement de l’UE.
Régime de financement
Régime de financement (ou «type d’action») à l’intérieur d’un programme présentant des caractéristiques communes. Le régime de financement précise le champ d’application de ce qui est financé, le taux de remboursement, les critères d’évaluation spécifiques pour bénéficier du financement et les formes simplifiées de couverture des coûts, telles que les montants forfaitaires.
Régime de financement (ou «type d’action») à l’intérieur d’un programme présentant des caractéristiques communes. Le régime de financement précise le champ d’application de ce qui est financé, le taux de remboursement, les critères d’évaluation spécifiques pour bénéficier du financement et les formes simplifiées de couverture des coûts, telles que les montants forfaitaires.
Coordinateur
7000 Stuttgart
Allemagne
Les coûts totaux encourus par l’organisation concernée pour participer au projet, y compris les coûts directs et indirects. Ce montant est un sous-ensemble du budget global du projet.