EURE utility wind farm project

Objectif



Objectives

In 1994 EURE members proposed the idea of a big European wind farm with the overall objective to prove the concept of large wind farms for utility application.
The project is to carry out the necessary Feasibility Study for a wind farm of approximately 100 MW. The immediate goals of the study are to show:
1. The technical viability of a large scale wind farm, based on megawatt-class wind turbines (i.e. in the range of 750 kW to 2 MW)
2. The quantification of the commercial risk of such a large utility wind farm
3. The clarification of legal, regulatory, partnership and logistic issues, in preparation for the eventual construction and operation of the wind farm by the EURE partners
4. The identification of those wind turbine models most appropriate for use on a large utility wind farm
(This study will consider all necessary aspects, such as questions of performance, reliability, electrical impact on the supply grid etc.) 5. The selection of the promising site(s)
(Up to three sites may be needed for the total output of about 100 MW) 6. The conduct of a required survey of the wind farm's expected social and environmental impact


Technical Approach

The completion of these goals will result in an advanced, but preliminary design of the wind farm(s), together with the development of an appropriate project management structure for construction.
Assuming the conclusion of the feasibility study is favorable, a proposal could then be put to the Commission for the construction and operation of the wind farm.
The following 14 European utilities and EURE members representing 10 countries decided to join the study that is coordinated by RWE Energie: Electrabel Belgium
Electricidade de Portugal Portugal
Electricité de France France
Elkraft Power Company Denmark
ENEL Italy
EVS Germany
Iberdrola Spain
Imatran Voima Oy Finland
National Wind Power Great Britain
PowerGen Great Britain
Public Power Corporation Greece
RWE Energie Germany
Compañia Sevillana Spain
Union Electrica Fenosa Spain

With this project the participating European utilities show their continuing commitment to the development of feasible options for renewable power generation.

Exploitation

The results of the project will be very important for the utilities, and other potential investors in wind energy equipments, on a local and even regional basis. The manufacturers will have also clear information about the needs of the users. A dissemination of this information will be so ensured to these energy actors.

Champ scientifique (EuroSciVoc)

Programme(s)

Thème(s)

Appel à propositions

Données non disponibles

Régime de financement

CSC - Cost-sharing contracts

Coordinateur

RWE Energie AG
Contribution de l’UE
Aucune donnée
Adresse
Kruppstraße 5
45128 Essen
Allemagne
Coût total
Aucune donnée

Participants (13)