Periodic Reporting for period 1 - SUPREME (Superconductor-Based Readiness Enhanced Magnetoplasmadynamic Electric Propulsion)
Période du rapport: 2023-06-01 au 2024-05-31
The SUPREME approach represents a significant milestone in European space technology by aiming to develop the first prototype EP system incorporating High-Temperature Superconductors (HTS). Building upon the advancements of the EU MEESST project, which successfully utilizes HTS coils for S/C re-entry shielding, SUPREME seeks to integrate HTS into AF-MPD thrusters. By developing, manufacturing, and testing a 5 kW AF-MPD thruster, SUPREME aims to showcase the integration of HTS coils. Additionally, the project will pioneer the development of a customized Power Processing Unit (PPU) for AF-MPD discharges, leveraging flight-qualified HET PPUs.
The method follows a structured space system development approach, aimed at advancing the prototype's design while effectively tracking progress through key milestones, staring with an initial system requirements study to establish a common baseline, followed by detailed design work on the AFM, a novel element and by integration of HTS coil technology. These concurrent activities are geared towards a unified CDR and SRR for final prototype validation before integration and testing.
A method has been developed to scale the 100 kW thruster IRS AF-MPD T SX3 down to the power of SUPREME of 5 kW. USTUTT's SX3 was used as one of the most successful AF-MPDTs in terms of operational features and high thrust efficiencies. This approach also lead to a magnetic field configuration for SUPREME that is geometrically similar to the one of SX3, which is considered a verifying element. The thermal analysis approved the design, confirming that the thruster can be operated almost continuously. A further element is the LaB6 cathode. The current design mitigates the life time issues that usual cathodes have. This cathode is designed, manufacturing is engaged. A new USTUTT facility to test hollow cathodes has been commissioned and set in operation. OES and thermo-structural characterization are possible. The output will functionally qualify the cathode and also serve for optimization campaigns. In contrast to the large SUPREME facility, it allows for specific characterisation and ad hoc investigations. This is a strong risk mitigation, as the SUPREME facility is accompanied by a high system complexity, and the time constraints of SUPREME in combination with the facility needs yield long test times. A modernization of the IRS facility for SUPREME was performed, implementing aspects such as automation of the evacuation process, modernization of the control systems, and vacuum quality optimization via implementation of a temperature control for the pump oil. A high precision thrust balance has been designed. This has benefited from the thruster scaling and analyses, where the expected thrust values have been used to enable sensor selection but also for balance design. An adaptation of chamber flange systems for interfaces has been established.
Interaction with CRISA, PEAK and UT to design PPU, PSU and HTSC systems for the test are highly entangled. The PPU, e.g. needed current and voltage levels and interface information to the facility. The HTSC interferes with geometries in the facility and a potential "thermal management" to control the maximum allowable temperature along copper routing and coil. Here, a trade has been made between the pressure level in the facility and thermal insulation needed. The aforementioned entanglement was a very important activity for the entire team, as only the combination of the know-how and the respective analysis tools made available by the different partners, making use of the previously developed requirements, allowed the development of the preliminary HTSC system for the test set-up, a preliminary PPU and PSU, hollow cathode, and thruster. A preliminary PPU has been established by Airbus Crisa based on the requirements settled by WP 2. PEAK has assessed information concerning relevant propellant feeding systems.
Results with a post PDR thruster design showed promising outcomes in terms of the thermo-structural behavior. This is a breakthrough as it approves SUPREME to be run in steady state. At the same time, the facility parameters in conjunction with the cryogenic system design (UT) confirm the feasibility of the cryo-system and the HTS coil employing MLI for the tests of SUPREME. This capability is be world-unique. Other entities (Japan, NZ, China, Russia) have tested w/o TMS, thus being able to test their systems only for short periods of time. Therefore, thruster and cathode cannot get to steady state leading to non-representative operation. The same applies to the erosion rates of the cathodes, an aspect that corresponds with limited life time.