Objectif
The Riso Hot Cell Facility, which was in operation for 26 years (1964-1990), comprises 6 concrete cells, lead cells, glove boxes, a shielded unit for temporary storage of waste until shipment, a frogman area, decontamination areas, workshops, various installations of importance for safe operation of the plant, offices, etc. The facility presented was used for physical and chemical post-irradiation investigations of various types of fuel pins (LWR, HTGR), including plutonium enriched pins.
The general objective of the decommissioning programme for the Hot Cell facility is to obtain a safe condition for the whole building that does not require the special safety provisions which were necessary for operation of the hot cell plant. As a result, the Hot Cell building will be usable for the other purposes.
Work includes the removal of all irradiated fuel items, of other radioactive items and of contaminated equipment, and decontamination of all cells and rooms. The project is expected to produce specific data on manpower, waste arisings and radiation exposures for the decommissioning of a total hot cell line.
The contractual work will lead to the identification of an assessed procedure appropriate for the decontamination and the dismantling of equipment of a hot cell line used for post-irradiation tests on nuclear fuel pins of different types.
The contractor will execute the work programme in co-operation with BNFL plc, Sellafield (UK), which is decommissioning the B 205 Fuel Reprocessing Pilot Plant, by using, to any suitable extent, common techniques, procedures and instrumentation.
The latest dose rate measurements determined after a former partial decontamination of a concrete cell were in the order of magnitude of 1-2 mGy/h.
The Risoe hot cell facility comprises 6 concrete cells, lead cells, glove boxes, a shielded unit for temporary storage of waste until shipment, a frogman area, decontamination areas, workshops, various installations of importance for safe operation of the plant, offices, etc. The facility was used for physical and chemical postirradiation investigations of various types of fuel pins. The general objective of the decommissioning programme for the hot cell facility is to obtain a safe condition for the whole building that does not require the special safety provisions which were necessary for operation of the hot cell plant. As a result, the hot cell building will be usable for other purposes. Work includes the removal of all irradiated fuel items, of other radioactive items and of contaminated equipment, and decontamination of all cells and rooms. The project is expected to produce specific data on manpower, waste arising and radiation exposures for the decommissioning of a total hot cell line.
The main efforts have been to remove fissile material, glove boxes, lead shielded steel boxes, the microscope and the tube transfer system, together with a large amount of scrap material from the concrete cell line. A few initial contamination and radiation measurements from a shutter between the cells, from the shutter housing and from one relatively clean cell have been analyzed.
WORK PROGRAMME
1. Removal of fissile material in the form of uranium oxides and uranium/plutonium mixed oxides
2. Removal of large contaminated equipment, including the power manipulator, the cell crane and all experimental equipment.
3. Removal of large contaminated facilities, including all lead-shielded steel boxes and glove boxes, the shielded storage facility, the conveyer, the microscope cell.
4. Decontamination of concrete cells by various procedures, with preceding and subsequent radiation measurements
4.1. Initial mapping of radiation levels in remote operation
4.2. Coarse cleaning by vacuum cleaning, conventional washing and possibly by special techniques
4.3. Final cleaning with conventional methods
4.4. Hot spot removal by special techniques.
5. Decontamination and radiological measurements of cell ventilators and ventilation ducts
6. Decontamination of room surfaces
7. Removal of active drains from various facilities
8. Generation of specific data on costs, radioactive job doses, working time and secondary waste arisings, derived from the execution of items 2 to 7.
Champ scientifique (EuroSciVoc)
CORDIS classe les projets avec EuroSciVoc, une taxonomie multilingue des domaines scientifiques, grâce à un processus semi-automatique basé sur des techniques TLN. Voir: Le vocabulaire scientifique européen.
CORDIS classe les projets avec EuroSciVoc, une taxonomie multilingue des domaines scientifiques, grâce à un processus semi-automatique basé sur des techniques TLN. Voir: Le vocabulaire scientifique européen.
- sciences naturelles sciences physiques optique microscopie
- ingénierie et technologie génie de l'environnement énergie et combustibles
Vous devez vous identifier ou vous inscrire pour utiliser cette fonction
Programme(s)
Programmes de financement pluriannuels qui définissent les priorités de l’UE en matière de recherche et d’innovation.
Programmes de financement pluriannuels qui définissent les priorités de l’UE en matière de recherche et d’innovation.
Thème(s)
Les appels à propositions sont divisés en thèmes. Un thème définit un sujet ou un domaine spécifique dans le cadre duquel les candidats peuvent soumettre des propositions. La description d’un thème comprend sa portée spécifique et l’impact attendu du projet financé.
Les appels à propositions sont divisés en thèmes. Un thème définit un sujet ou un domaine spécifique dans le cadre duquel les candidats peuvent soumettre des propositions. La description d’un thème comprend sa portée spécifique et l’impact attendu du projet financé.
Appel à propositions
Procédure par laquelle les candidats sont invités à soumettre des propositions de projet en vue de bénéficier d’un financement de l’UE.
Données non disponibles
Procédure par laquelle les candidats sont invités à soumettre des propositions de projet en vue de bénéficier d’un financement de l’UE.
Régime de financement
Régime de financement (ou «type d’action») à l’intérieur d’un programme présentant des caractéristiques communes. Le régime de financement précise le champ d’application de ce qui est financé, le taux de remboursement, les critères d’évaluation spécifiques pour bénéficier du financement et les formes simplifiées de couverture des coûts, telles que les montants forfaitaires.
Régime de financement (ou «type d’action») à l’intérieur d’un programme présentant des caractéristiques communes. Le régime de financement précise le champ d’application de ce qui est financé, le taux de remboursement, les critères d’évaluation spécifiques pour bénéficier du financement et les formes simplifiées de couverture des coûts, telles que les montants forfaitaires.
Coordinateur
ROSKILDE
Danemark
Les coûts totaux encourus par l’organisation concernée pour participer au projet, y compris les coûts directs et indirects. Ce montant est un sous-ensemble du budget global du projet.