DECOMMISSIONING OF THE RISO HOT CELL FACILITY

Ziel

The Riso Hot Cell Facility, which was in operation for 26 years (1964-1990), comprises 6 concrete cells, lead cells, glove boxes, a shielded unit for temporary storage of waste until shipment, a frogman area, decontamination areas, workshops, various installations of importance for safe operation of the plant, offices, etc. The facility presented was used for physical and chemical post-irradiation investigations of various types of fuel pins (LWR, HTGR), including plutonium enriched pins.

The general objective of the decommissioning programme for the Hot Cell facility is to obtain a safe condition for the whole building that does not require the special safety provisions which were necessary for operation of the hot cell plant. As a result, the Hot Cell building will be usable for the other purposes.

Work includes the removal of all irradiated fuel items, of other radioactive items and of contaminated equipment, and decontamination of all cells and rooms. The project is expected to produce specific data on manpower, waste arisings and radiation exposures for the decommissioning of a total hot cell line.

The contractual work will lead to the identification of an assessed procedure appropriate for the decontamination and the dismantling of equipment of a hot cell line used for post-irradiation tests on nuclear fuel pins of different types.

The contractor will execute the work programme in co-operation with BNFL plc, Sellafield (UK), which is decommissioning the B 205 Fuel Reprocessing Pilot Plant, by using, to any suitable extent, common techniques, procedures and instrumentation.

The latest dose rate measurements determined after a former partial decontamination of a concrete cell were in the order of magnitude of 1-2 mGy/h.
The Risoe hot cell facility comprises 6 concrete cells, lead cells, glove boxes, a shielded unit for temporary storage of waste until shipment, a frogman area, decontamination areas, workshops, various installations of importance for safe operation of the plant, offices, etc. The facility was used for physical and chemical postirradiation investigations of various types of fuel pins. The general objective of the decommissioning programme for the hot cell facility is to obtain a safe condition for the whole building that does not require the special safety provisions which were necessary for operation of the hot cell plant. As a result, the hot cell building will be usable for other purposes. Work includes the removal of all irradiated fuel items, of other radioactive items and of contaminated equipment, and decontamination of all cells and rooms. The project is expected to produce specific data on manpower, waste arising and radiation exposures for the decommissioning of a total hot cell line.

The main efforts have been to remove fissile material, glove boxes, lead shielded steel boxes, the microscope and the tube transfer system, together with a large amount of scrap material from the concrete cell line. A few initial contamination and radiation measurements from a shutter between the cells, from the shutter housing and from one relatively clean cell have been analyzed.
WORK PROGRAMME

1. Removal of fissile material in the form of uranium oxides and uranium/plutonium mixed oxides

2. Removal of large contaminated equipment, including the power manipulator, the cell crane and all experimental equipment.

3. Removal of large contaminated facilities, including all lead-shielded steel boxes and glove boxes, the shielded storage facility, the conveyer, the microscope cell.

4. Decontamination of concrete cells by various procedures, with preceding and subsequent radiation measurements

4.1. Initial mapping of radiation levels in remote operation
4.2. Coarse cleaning by vacuum cleaning, conventional washing and possibly by special techniques
4.3. Final cleaning with conventional methods
4.4. Hot spot removal by special techniques.

5. Decontamination and radiological measurements of cell ventilators and ventilation ducts

6. Decontamination of room surfaces

7. Removal of active drains from various facilities

8. Generation of specific data on costs, radioactive job doses, working time and secondary waste arisings, derived from the execution of items 2 to 7.

Wissenschaftliches Gebiet (EuroSciVoc)

CORDIS klassifiziert Projekte mit EuroSciVoc, einer mehrsprachigen Taxonomie der Wissenschaftsbereiche, durch einen halbautomatischen Prozess, der auf Verfahren der Verarbeitung natürlicher Sprache beruht. Siehe: Das European Science Vocabulary.

Sie müssen sich anmelden oder registrieren, um diese Funktion zu nutzen

Programm/Programme

Mehrjährige Finanzierungsprogramme, in denen die Prioritäten der EU für Forschung und Innovation festgelegt sind.

Thema/Themen

Aufforderungen zur Einreichung von Vorschlägen sind nach Themen gegliedert. Ein Thema definiert einen bestimmten Bereich oder ein Gebiet, zu dem Vorschläge eingereicht werden können. Die Beschreibung eines Themas umfasst seinen spezifischen Umfang und die erwarteten Auswirkungen des finanzierten Projekts.

Aufforderung zur Vorschlagseinreichung

Verfahren zur Aufforderung zur Einreichung von Projektvorschlägen mit dem Ziel, eine EU-Finanzierung zu erhalten.

Daten nicht verfügbar

Finanzierungsplan

Finanzierungsregelung (oder „Art der Maßnahme“) innerhalb eines Programms mit gemeinsamen Merkmalen. Sieht folgendes vor: den Umfang der finanzierten Maßnahmen, den Erstattungssatz, spezifische Bewertungskriterien für die Finanzierung und die Verwendung vereinfachter Kostenformen wie Pauschalbeträge.

CSC - Cost-sharing contracts

Koordinator

RISOE NATIONAL LABORATORY
EU-Beitrag
Keine Daten
Adresse
Frederiksborgvej 399
ROSKILDE
Dänemark

Auf der Karte ansehen

Gesamtkosten

Die Gesamtkosten, die dieser Organisation durch die Beteiligung am Projekt entstanden sind, einschließlich der direkten und indirekten Kosten. Dieser Betrag ist Teil des Gesamtbudgets des Projekts.

Keine Daten
Mein Booklet 0 0