Periodic Reporting for period 2 - THUMBS UP (Thermal energy storage solUtions to optimally Manage BuildingS and Unlock their grid balancing and flexibility Potential)
Berichtszeitraum: 2024-05-01 bis 2025-08-31
To achieve such overall objective, THUMBS UP will realise and demonstrate PCM and TCM based solutions with the following key metrics:
- Size: modular solutions from 3 to 100 kWh to guarantee TES integration in different building area.
- Energy Density: target 65 kWh/m3 for short-duration TES, 120 kWh/m3 for long duration TES (4 weeks after charge) at system level.
- Competitive costs: target 140 €/kWh for short duration TES and 200 €/kWh for long duration TES.
Complete design and development of the integrated FractLES system, including PCM development, HEX plate optimisation and control system definition. System manufacturing and delivery to the validation site. The scaling up of the composite sorbent manufacturing for the SorTES was completed, a novel design of the reactor was finalized to maximize the amount of sorbent material, and a model-based SoC and SoH monitoring approach was finalized.
Completion of building preparation and engineering designs, definition and scheduling of installation and permitting activities, development of the demonstration campaign calendar, delivery and initial validation of TES prototypes, progress in BEMS development and integration.
First LCA of the pilots and complete LCA of FractLES solution, full regulatory assessment and full PESTLE Analysis, first wide survey to analyse social acceptability, identification and data gathering from the replication buildings, preliminary DHN impact simulations.
- will be compact, reliable, cost effective and easy-to-install. FractLES and SorTES systems guarantee high density (up to 65 kWh/m3 and 120 kWh/m3 respectively) and modularity. They will be tested in different climates and conditions (both connected and non-connected buildings – single family, multi family, tertiary buildings), also to facilitate building integration in DHNs. Thanks to THUMBS UP systems RES equipped buildings will also have a lower impact on both electric and thermal grid.
- will have relevant energy density that will enable the realisation of compact solutions (Modular TES “wardrobe”/thermal battery) at different scale (to be installed in flats/rooms, basement/technical rooms, horizontal/vertical distribution) and easily coupable to HP and low temperature distribution H&C solutions. It will be studied how to “pre-assembly” as much as possible the systems to minimise installation periods as comparable as boiler ones. The absence of hazardous fluids/materials will guarantee the potential installation everywhere in a building without special permits.
- will enable PtH approach at hourly/daily/weekly level, facilitating peak shifting of RES (both thermal and PV) as well as potential heat interexchange with DHN and other buildings. Aggregation of TES at building (if distributed in flats/levels) and district level, will make buildings as grid flexibility actors to maximise RES penetration and exploitation and reduce grid bothering.
- aims to realise cost competitive TES solutions targeting 140 €/kWh for FractLES/short duration TES and 200 €/kWh for SorTES/long duration TES. Thanks to THUMBS UP TES local heating system will operate at higher efficiency, local RES will be better exploited and buildings could sell heat to DHN and grid flexibility services to DSO, thus driving to a PBP lower than 8 yrs at building level.