Periodic Reporting for period 1 - POWDER2POWER (MW-scale fluidized particle-driven CSP prototype demonstration)
Berichtszeitraum: 2023-10-01 bis 2025-01-31
- Determine particle flow properties as a function of temperature
- Determine erosion, attrition and dust emission of particles
- Assessment of particle transport issues at pilot and commercial scale
- Design and construction of the particle conveyance system for the P2P pilot plant
- Design of the particle electrical heater
- Improvement of the solar receiver instrumentation and control system
- Preparation of the installation of power block components at ground level
- Definition of up-scaled integrated P2P power plant layouts, including PV+heaters hybridisation
- Design of a utility-scale heliostat field and solar receiver
- Design of a utility-scale electrical heating system
- Design of a utility-scale sCO2 cycle
- Determination of solar field and receiver operational maps
- Determination of Power block operational maps
- LCOE calculation
- Cost functions and KPI definition
- Environmental Impact Assessment via LCA
- How to efficiently move hot particles
- How to simulate a CSP hybrid process with hot particles
- Know-how to move hot particles vertically
- Know-how to optimise efficiency and cost of hybrid CSP plans
- Contribution to widespread CSP and particles process technologies to renewable energies and green societies