Periodic Reporting for period 1 - INITIATE (Innovative industrial transformation of the steel and chemical industries of Europe)
Berichtszeitraum: 2020-11-01 bis 2022-04-30
The INITIATE project will take all necessary steps to provide the basis for the roll-out of a 1st commercial size demonstrator at 50 kt/y urea in the basis of basic oxygen furnace gas (BOFG). Operational reliability of the technological innovations is demonstrated in a pilot plant at TRL-7. The energy, economic and environmental advantages are assessed via the verification of the key-performance indicators of the concept and comparing them with a reference and base cases. Next, a bankable design of the First-Of-A-Kind (FOAK) commercial plant is made to convert BOFG to AdBlue® and/or another NH3 based product. For the successful implementation beyond the FOAK plant, a long-term implementation plan is developed. The synergies on local and European scale are identified, considering industrial infrastructures and other symbiotic systems. For this, stakeholder alignment is required and licensing strategies are developed to ensure successful future deployment.
Communication and dissemination of the project results are organized through the project website, the associated newsletter and via the organization of workshops etc.
For the novel concept of BOFG to NH3, the definition of catalysts and sorbents is in progress. The contaminants present in the BFG and BOFG can influence the material choice and pilot lay-out. In parallel to a literature review and the input from the expert end-users AM and SSAB, extensive contaminant measurement campaigns are performed at SSAB for BOFG, and at AM for BFG and BOFG. This resulted in a detailed overview of the type and level of contaminants that may be expected. As the pilot uses the SSAB BOFG, the pilot clean-up section upstream the ammonia loop is defined. Nevertheless, tailored investigations of the contaminants per site is mandatory as the gas composition can vary significantly, although no showstoppers have been identified.
To assess the energy, economic and environmental advantages of the INITIATE concept, the bases for the techno-economic analysis (TEA) as well as the life-cycle assessment (LCA) have been defined. For the TEA, the base and reference cases have been defined and summarized in the public deliverable D5.1. The base cases cover stand-alone iron & steel and ammonia & urea plants. In the reference cases integrated amine based decarbonization is applied to the stand-alone plants. The life-cycle-inventory as well as the boundary conditions have been established. Accordingly, robust bases are created for benchmarking of the INITIATE concept against next best available technologies using carefully selected key-performance indicators.
For the roll-out of the FOAK commercial plant, site identification and evaluation has begun, resulting in discussions with several commercial parties. Implementation beyond the FOAK plant requires mapping of the symbiotic potential. The potential product market combinations were listed in brainstorm sessions and interviews with different stakeholders. Next, their validity is assessed by analyzing their technological and sociological key-performance-indicators.
The communication and dissemination plan was submitted, while launching the project visual identity and the website. The website highlights news a and project results and a newsletter is issued. Additionally, the 1st workshop was organized on funding opportunities for the development of CCU. With the CORALIS project mutual dissemination and communication efforts are explored.
A data management plan and a risk register were submitted. The early identification and evaluation of risks, allow adequate risk management. All partners are encouraged to actively addressed and assessed risks. 6 monthly progress meetings, separate exploitation board and executive team meetings as well as discussions with the External Advisory Board have been organized.
The impacts and wider societal implications of the project will become apparent as the associated work packages start producing results later in the project. Nevertheless, the bases has been laid. Next to the definition of base and reference cases for the TEA and the LCA, further symbiotic concepts has been listed. All these activities aim to establish a bankable design of the 1st commercial plant to be located in Europe.