WP1: Coordination and Management: The Project Management Board had 5 meetings for coordination and carried out the coaching sessions provided by the EASME. From month 1 the project is being monitored and the relevant information recorded in order to complete the Progress Report and the Final Report.
WP2: The mold required to manufacture both types of prototypes was integrated in the company on month 1.The UHC components were purchased and the prototypes construction started on month 2. At this moment, the construction of the rafts is in the following stage:
Raft 1: Mixta. 100% finished in month 5. Floating in O Grove (Galicia). The streaming of the raft floating can be seen at IDIFOR youtube channel
Raft 2: Plus. 100% finished in month 6. Expected to float in month 7 in Galicia
Raft 3: Plus. 35% finished. Expected to float in Galicia in month 8.
The manufacturing process is used to acquire know-how and to optimize the industrial production. The production team has studied the problems, bottle-necks, difficulties and experiences.
WP3: Documentation process and product development: An statistically representative plan of tests was defined according to the quality control requirements of the concrete guidelines, and the material is being controlled according to it. The learning acquired during WP2 is already being integrated in the design of the new prototypes and the rafts demanded.
WP4: Large-scale demonstration
The first raft has been transported to Galicia and assembled in intertidal zone. The experience assembling the Formex®Mixta raft was that it required five days including the installation of the wooden joists. The transport of the second raft was done on month 7 and it will be assembled on month 7.
Video cameras for the live streaming the rafts were already installed on the first raft, and the sensors for corrosion measurement integrated in the beams of the three rafts manufactured.
WP5: Business and commercialization strategy
The consortium has been in contact with stakeholders and potential clients, perceiving the market expectations. Members of the Management team have visited Galicia already four times. A customer profile analysis is being carried out based on the meetings with the raft assemblers, institutions involved (Xunta de Galicia mainly) and the prototype testers . The team is also learning with the frequent conversations with the farmers that want to test the rest of the prototypes.
Finally, the utility model was requested in France, Italy, and Chile. The team also requested the registration of the brand under Nice class 19 in Portugal, France and Morocco.
WP6: Communication activities
The reports focused on the advanced materials sector (D6.2) and another on the aquaculture sector (D6.3) are being written and will be published in Open Access. The abstract for the aquaculture congress was submitted in month 6. Besides, it was published in two different newspaper articles the innovative raft. Besides, the company RDC will give a lecture invited by SEIMED-EEN on May 18th (month 7) in Alicante (Spain) and in Valencia in month 11 to explain the project as a case of success in SME Instrument of H2020. The main project website (www.idifor.com) has been developed in both languages. The site has the name of the joint venture created by the consortium members for the future exploitation of the business. The team has created for IDIFOR the Youtube Channel, Linkedin and Twitter, mentioning at all cases the support received from the SME Instrument project granted.