The activities of the 1st project period focused on the elaboration of the requirements for the battery (aging, BMS, etc.), recycling, wheels, chassis and the definition of the software platform.
Based on this, activities in the 2nd led to the following results:
WP1 System requirements, use cases and validation methodologies
The first work package was finished in April 2018. The requirements for battery (aging, BMS, etc.), recycling, wheels, chassis and the definition of Software platform and of preliminary risks were completed
WP2 Simulation and modelling for seamless integration
This work package started in November 2017 and is still going on. Work on Model testing toolkit and FMI Composer integration has started as well as the first Amesim vehicle model simulation.
WP3 Safety
The Cell safety and aging characterization is ongoing. The first definition of abuse test procedure and measured parameters are partly specified.
WP4 Integration
Starts in January 2018 and is still ongoing. Development of the ECU board that will communicate with the BMS and the components are defined as well as the design parameters for vehicle´s wheel development.
WP5 Validation and KPI
The Validation and KPI work package started in April 2019.
WP6 Dissemination and Exploitation
Multiple dissemination activities were performed by the partners such as presentations at conferences, workshops and articles for scientific and non-scientific journals. All publications were uploaded to the Zenodo repository for open access as well as to the DEMOBASE website: www.demobase-project.eu/dissemination/
WP7 Management and Coordination
The project has been initialized, including the setup of the project bodies and the initiation of the internal management and communication processes. The project progress, the quality of the project results as well as the project risks were monitored with respect to the project plan by the Coordinator and the General Assembly. Regular technical meetings ensured a continuous communication between the partners for an optimal exploitation of synergies