Periodic Reporting for period 1 - CLUG 2.0 (CLUG Demonstration of Readiness for Rail)
Periodo di rendicontazione: 2023-02-01 al 2024-01-31
The main objectives of the CLUG 2.0 project are listed below:
• To review, consolidate and complete the high-level user needs and system requirements for the LOC-OB System including Start of Mission and Track Selectivity.
• To consolidate the safe localisation system architecture and to further prototype the functions of the CLUG LOC-OB.
• To consolidate by live demonstration the readiness of the CLUG LOC-OB multi-sensor fusion algorithms.
• To perform an analysis of Reliability, Availability, Maintainability, and Safety (RAMS) on the consolidated functional architecture of the system.
The primary impact of the LOC-OB System is to diminish reliance on trackside equipment for train localization, such as Eurobalises and other prevalent devices currently used in the railway industry for train tracking.The LOC-OB system facilitates a transition towards moving block operations (ERTMS/ETCS Level 3). When paired with onboard train integrity devices, it paves the way for a future railway system devoid of track circuits and axle counting systems, significantly contributing to waste reduction. Following this, CLUG 2.0 fosters an interoperable, sustainable, and eco-friendly mobility system, significantly reducing the transportation sector’s environmental impact. Its integration with advanced traffic management and automated train control allows for notable energy savings, thereby aiding in climate change mitigation and greenhouse gas reduction.
The CLUG 2.0 activity will continue in Europe’s Rail Joint Undertaking with a main goal of capitalizing the work performed in CLUG 2.0 to demonstrate a complete CLUG LOC-OB prototype demonstration in the frame of the Innovation Pillar of the ERJU program.
1. LOC-OB requirements (WP2) were defined and consolidated using as a basis the CLUG project outcomes on this topic and considering the user needs, operational context, initial assumptions and system boundary also defined on this first period (WP2)
2. The system context analysis and RAMS activities plan were completed together with the preliminary Hazard Analysis (WP3).
3. The CLUG 2.0 consortium focused on addressing the development of LOC-OB critical functions to demonstrate its functional architecture (WP4) for train localisation in ERTMS level 2 and preparing level 3. The algorithms already started in the first period will be completed in the second one.
4. Test trains were equipped with a complete measuring system for collecting sensor data and the developed site demonstrator onboard.
5. The preparation of the Onboard Site Demonstrator has started but not fully completed at the moment of this intermediate report.
The RAMS analysis (WP3), algorithms development (WP4) and Integration and Testing (WP5) activities were launched and partially completed in this period but would be finalised and reported in the final one.