- The Technical and non-technical requirements for the entire project have been formally specified in the earliest phase of the project together with the KPIs:
• Definition of 279 requirements categorized into eleven classification groups.
• Definition of 53 KPIs
- The uses cases to address the interest of the demonstration sites and to ensure the transferability of the results, have been described in detail. The SGAM architecture of these Use Cases has also been designed.
The project has defined 47 Use Cases, which the respective SGAM design, categorized under 4 High Level Use Cases:
- The project has studied the energy regulatory framework of SEE countries.
Analysis of the regulatory and social conditions of different energy operation and market aspects of the 8 pilot countries.
- The project has studied the physical and ICT infrastructure of TRINITY end-users.
Analysis of:
• 1 RSC.
• 5 TSOs.
• 2 RES Producers.
• 4 Market Operators.
- The project provided 4 different products and three extra modules.
• Design of the four TRINITY products already performed.
• The first and second version of all the technologies have been delivered in due time as can be shown in the deliverables from WP3, WP4, WP5 and WP6.
- The project consortium has participated and organized several dissemination activities, in order to increase the project impact, to spread TRINITY benefits and outputs among different stakeholders and to create synergies with other projects.
• Participation in 64 events.
• The website reached 7900 visits.
• TRINITY’s social networks have 570 followers.
• TRINITY has produced a total of 14 videos.
• Number of scientific publications: 7 publications.
- The demonstration activities started and were performed in due time.
All the deployment and demonstration activities of the different TRINITY technologies were performed and reported in WP7 deliverables.
- Exploitation activities started and were performed in due time.
D1.6 reports all the exploitation activities performed. Identification of KERs, characterization, risk analysis, IPR strategy etc.
- Replication potential of the project was analyzed.
TRINITY replication was analyzed following 5 axes, one per Task: Cost Benefit analysis, impact assessment, identification of barriers, Maaret coupling roadmap and standardization potential. Deliverables from WP8 report these activities and were submitted in due time.
-Reporting
In summary, the project submitted all the Deliverables in due time and provided all the required information for the different Periodic Reports (both financial and technical).