The main activities developed under Phase I are summarized below:
Technical Viability Assessment:
- Definition of the different parts of the Multi-AD system at an industrial level with the objective of reducing the organic load of the influent by 90%, producing a biogas with a high content of methane (80%) and being self-sufficient in terms of energy. Specifically, the following parts have been considered: anaerobic reactor, mixing tank, instrumentation, external recirculation circuit and biogas line.
- Analysis of the advanced control system that will be integrated to fully automate the process.
- Approach of the technical validation of the first Multi-AD industrial prototype in a Spanish winery, to be conducted during both harvest and non-harvest periods. The main parameters will be monitored and the operational conditions will be analyzed to evaluate the performance of the unit.
- Definition of the Multi-AD production and installation process.
Commercial Viability Assessment:
- Analysis of the European agri-food sector and of the main characteristics of the wastewater generated in each sub-sector to determine the viability of the implementation of Multi-AD technology.
- Evaluation of the size of the market and the volume of business. Besides, other key aspects have been studies, such as: the innovation character of the EU F&D industry, total expenditure in R&D on innovation and the percentage of it allocated to technologies and processes to reduce the carbon footprint and pollution of water resources.
- Financial projections of Multi-AD commercialisation, to determine the payback period of the investment.
-Analysis of the two main markets for the implementation of Multi AD technology:
i) Beverage production sector, specifically wineries
ii) Fruit and vegetable processing sector.
In addition, other markets that may be affordable for the implementation of the Multi AD system have been explored (i.e. dairy sector).
Financial Viability Assessment:
- Calculation of the cost of a Multi-AD unit of 100 m3 on the basis of the unit cost of each component of the system according to the current prices of the AEMA´s suppliers. Estimation of the cost of the Multi-AD system depending on the volume of the reactor, from 25 to 500 m3.
- Analysis of the financing strategy foreseen both of own resources and external resources.
- Estimation of the business plan, sales and benefits for AEMA during the 5 years after the end of the project, between 2021 and 2025.