• WP1: Project Management Plan completed and issued 26th March 2021
• WP2: Although delayed (6 month+) by COVID we are currently in advanced discussions with end users regarding three potential host sites, situated in Germany, Italy and Ireland. Outline design and costings are being undertaken and detailed design will follow once the final preferred host site has been established.
• WP3: The cumulative effects of COVID have impacted on this activity which will commence after detailed design (WP2) has been undertaken.
• WP4/5: COVID has prevented face to face meetings with potential Partners and End Users and our attendance at industry events. To mitigate the impact, we have commissioned a consultant to facilitate initial introductions. Using web-based technologies, we have undertaken and recorded in our Sales and Partner Pipeline Report, meetings with 31 potential partners and 23 potential end users spread across Sweden, Holland, Germany, Belgium, Spain, Portugal, UK, Ireland, Italy, Denmark, Sweden and Norway.