This project report includes all the project period from the beginning to its closure after 48 month running.
During this working period corresponding to the 48 months WP1, WP2, WP3, WP4, WP5, WP6 and WP7 have been finished and final results from performed activities are as follows:
• R1 - A group of new heat exchanger equipment (2 prototypes): one for high temperature heat exchange and another for low temperature heat exchange will be developed.
• R2 - A Borehole Thermal Energy storage unit (BTES) with two different levels of heat storage will be developed
• R3 – Expert knowledge on PCM selection, integration and use including equipments construction and safety measures
• R4 – Expert knowledge on Heat Transfer Fluid for high energy recovery exhaust gases (800ºC) selection, integration and use including equipments construction and safety measures.
• R5 - Smart Management System, with an adapted methodology for process monitoring and control, to be integrated in the ISO 9100 of the plant.
• R6 – Energy savings due to running energy recovery system
• R7 – Industrial system for energy recovery.
The dissemination has taken place over different congresses and fairs StatusPrediction of lifetime of critical components for energy efficient installations /Tribology International/Lubmat (C) 2016/International Conference “Environmental Engineering”, Vilnius, 28 April 2017/ Geoner 2017 V Congreso de energía geotérmica aplicado a la edificación y a la industria , Madrid, 26 Abril 2017, Energy day Durango 2018, GIFA Düsseldorf 2019